TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/34621/2018              (ii). Name of Project for which Forest Land is required : Kurukshetra to Amin Railway Station              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Widening of road from Kurukshetra to Amin upto Railway Station Amin Km 0.00 to 9.99 (RD 0.00 to 3.65) under Forest Division Kurukshetra              (iv). File no. : 9-HRB022-2019-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.616
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HR/ROAD/34621/201809/07/201829/08/2018  16/07/2018   13/09/2018  10/08/2018   13/09/2018   18/10/2018 Kurukshetra :18/10/2018North Circle Panchkula:
  25/01/2019 (Kurukshetra)

Haryana:
29/01/2019
Haryana:
12/02/2019
Chandigarh:
12/02/2019
25/06/2019
By :Regional Office
Haryana
06/07/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:21/02/2019  
Replied by State Government(Haryana) on:19/06/2019  
Query raised by State Government (Haryana) on:25/02/2019  
Replied by Nodal Officer (Haryana) on:19/06/2019  
Query raised by Nodal Officer (Haryana) on:25/02/2019  
Replied by Circle(North Circle Panchkula) on:11/03/2019  
Query raised by Circle (North Circle Panchkula) on:27/02/2019  
Replied by DFO (Kurukshetra) on:05/03/2019  
Query raised by DFO (Kurukshetra) on:05/03/2019  
Replied by UA on :05/03/2019  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:04/11/2020  
Query raised by State Government (Haryana) on:09/08/2021  
Query raised by Nodal Officer on:09/08/2021  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .