TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/25818/2017              (ii). Name of Project for which Forest Land is required : Construction of ROB              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.378 ha of forest land for Construction of ROB in lieu of level crossing no. 22 at km 43.405 of Rohtak Rewari railway line on crossing of Jhajjar Kosli road SH-22 at Jhajjar (Haryana              (iv). File no. : 9-HRB177-2017-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.378
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HR/ROAD/25818/201724/04/201727/04/2017   07/06/2017   08/06/2017   28/06/2017 Jhajjar(Central Rohtak) :05/07/2017Central Circle Rohtak:
  13/11/2017 (Jhajjar(Central Rohtak))

Haryana:
27/11/2017
Haryana:
12/12/2017
Chandigarh:
12/12/2017
27/03/2018
By :Regional Office
Haryana
05/12/2018
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:11/01/2018  
Replied by State Government(Haryana) on:21/03/2018  
Query raised by State Government (Haryana) on:16/01/2018  
Replied by Nodal Officer (Haryana) on:21/03/2018  
Query raised by Nodal Officer (Haryana) on:16/01/2018  
Replied by Circle(Central Circle Rohtak) on:24/01/2018  
Query raised by Nodal Officer (Haryana) on:13/03/2018  
Replied by Circle(Central Circle Rohtak) on:15/03/2018  
Query raised by Nodal Officer (Haryana) on:20/03/2018  
Replied by Circle(Central Circle Rohtak) on:20/03/2018  
Query raised by Circle (Central Circle Rohtak) on:17/01/2018  
Replied by DFO (Jhajjar(Central Rohtak)) on:24/01/2018  
Query raised by Circle (Central Circle Rohtak) on:13/03/2018  
Replied by DFO (Jhajjar(Central Rohtak)) on:15/03/2018  
Query raised by Circle (Central Circle Rohtak) on:20/03/2018  
Replied by DFO (Jhajjar(Central Rohtak)) on:20/03/2018  
Query raised by DFO (Jhajjar(Central Rohtak)) on:19/09/2017  
Replied by UA on :10/10/2017  
Query raised by DFO (Jhajjar(Central Rohtak)) on:26/10/2017  
Replied by UA on :03/11/2017  
Query raised by DFO (Jhajjar(Central Rohtak)) on:20/03/2018  
Replied by UA on :20/03/2018  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:04/11/2020  
Query raised by State Government (Haryana) on:31/07/2021  
Query raised by Nodal Officer on:31/07/2021  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .