TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/21790/2016              (ii). Name of Project for which Forest Land is required : 4-Lanning from Km.3.335 to 3.675 & 4.575 to 6.875 on Bhiwani-Mundal-Jind-Karnal road New NH-709A              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for diversion of forest land for 4-Lanning from Km.3.335 to 3.675 & 4.575 to 6.875 (Bhiwani District) on Bhiwani-Mundal-Jind-Karnal road new NH-709A is required because existing width of the road is inadequate to cater the heavily increased volume of traffic. The town frequently suffer traf              (iv). File no. : 9-HRB052-2017-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.0096
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/ROAD/21790/201625/10/201601/12/2016  23/11/2016  08/11/2016   01/12/2016  25/11/2016  15/11/2016   01/12/2016   06/12/2016 Bhiwani(West Circle Hissar) :13/12/2016West Circle Hissar:
  23/01/2017 (Bhiwani(West Circle Hissar))

Haryana:
09/02/2017
Haryana:
17/02/2017
Chandigarh:
08/03/2017
22/08/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:17/03/2017  
Replied by State Government(Haryana) on:22/05/2017  
Query raised by Regional Office (Chandigarh) on:22/06/2017  
Replied by State Government(Haryana) on:16/08/2017  
Query raised by State Government (Haryana) on:24/03/2017  
Replied by Nodal Officer (Haryana) on:22/05/2017  
Query raised by State Government (Haryana) on:13/07/2017  
Replied by Nodal Officer (Haryana) on:16/08/2017  
Query raised by Nodal Officer (Haryana) on:24/03/2017  
Replied by Circle(West Circle Hissar) on:07/04/2017  
Query raised by Nodal Officer (Haryana) on:19/04/2017  
Replied by Circle(West Circle Hissar) on:21/04/2017  
Query raised by Nodal Officer (Haryana) on:16/05/2017  
Replied by Circle(West Circle Hissar) on:16/05/2017  
Query raised by Nodal Officer (Haryana) on:13/07/2017  
Replied by Circle(West Circle Hissar) on:03/08/2017  
Query raised by Nodal Officer (Haryana) on:10/08/2017  
Replied by Circle(West Circle Hissar) on:16/08/2017  
Query raised by Circle (West Circle Hissar) on:24/03/2017  
Replied by DFO (Bhiwani(West Circle Hissar)) on:07/04/2017  
Query raised by Circle (West Circle Hissar) on:20/04/2017  
Replied by DFO (Bhiwani(West Circle Hissar)) on:21/04/2017  
Query raised by Circle (West Circle Hissar) on:16/05/2017  
Replied by DFO (Bhiwani(West Circle Hissar)) on:16/05/2017  
Query raised by Circle (West Circle Hissar) on:18/07/2017  
Replied by DFO (Bhiwani(West Circle Hissar)) on:02/08/2017  
Query raised by Circle (West Circle Hissar) on:10/08/2017  
Replied by DFO (Bhiwani(West Circle Hissar)) on:16/08/2017  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:20/04/2017  
Replied by UA on :21/04/2017  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:16/05/2017  
Replied by UA on :16/05/2017  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:18/07/2017  
Replied by UA on :21/07/2017  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:10/08/2017  
Replied by UA on :10/08/2017  