Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Fatehabad)
|
EDS
|
User Agency (pdfatehabad@gmail.com)
|
02/08/2021
|
Pls do the needful as per letter issued to you
|
|
2
|
User Agency (pdfatehabad@gmail.com)
|
REPLY
|
DFO (Fatehabad)
|
30/12/2021
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
21/01/2022
|
Revise CA Scheme with new rate of NPV as per Guideline
|
|
4
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
21/01/2022
|
Revise CA Scheme with new rate of NPV as per Guideline
|
|
5
|
DFO (Fatehabad)
|
REPLY
|
CF (West Circle Hissar)
|
28/01/2022
|
Forwarding Letter with Check List-18 & 16 online uploaded. (New NPV Rates)
|
|
6
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
28/01/2022
|
Forwarding Letter with Check List-18 & 16 online uploaded. (New NPV Rates)
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
29/03/2022
|
eds
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
08/04/2022
|
upload the information for further necessary action
|
|
9
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
08/04/2022
|
upload the information for further necessary action
|
|
10
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
08/04/2022
|
upload the information for further necessary action
|
|
11
|
DFO (Fatehabad)
|
EDS
|
User Agency (pdfatehabad@gmail.com)
|
18/05/2022
|
Please Remove the Objection and Online Upload.
|
|
12
|
User Agency (pdfatehabad@gmail.com)
|
REPLY
|
DFO (Fatehabad)
|
29/04/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Fatehabad)
|
REPLY
|
CF (West Circle Hissar)
|
02/05/2023
|
Online Objection removed, Letter attached.
|
|
14
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
03/05/2023
|
Online Objection removed, Letter attached.
|
|
15
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
26/05/2023
|
Coloured Toposheet of CA site with number and countersigned by DFO needs to be uploaded on portal.
|
|
16
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
29/05/2023
|
Coloured Toposheet of CA site with number and countersigned by DFO needs to be uploaded on portal.
|
|
17
|
DFO (Fatehabad)
|
REPLY
|
CF (West Circle Hissar)
|
01/06/2023
|
Coloured Toposheet of CA site with number and countersigned by DFO uploaded on portal.
|
|
18
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
01/06/2023
|
Coloured Toposheet of CA site with number and countersigned by DFO uploaded on portal.
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
09/06/2023
|
EDS Reply
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
13/06/2023
|
EDS removed case sent to RO for stage I Approval
|
|