| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Hisar)
|
EDS
|
User Agency (pwd-eepd-hansi@hry.nic.in)
|
22/04/2021
|
EDS Raised
|
|
|
2
|
User Agency (pwd-eepd-hansi@hry.nic.in)
|
REPLY
|
DFO (Hisar)
|
05/05/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
21/05/2021
|
Site inspection report of CCF be uploaded
|
|
|
4
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
21/05/2021
|
Site inspection report of CCF uploaded
|
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
07/06/2021
|
eds
|
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
11/06/2021
|
eds
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
11/06/2021
|
eds
|
|
|
8
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
17/06/2021
|
eds
|
|
|
9
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
23/06/2021
|
EDS Removed
|
|
|
10
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
28/06/2021
|
As per DFO EDS Removed
|
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
08/07/2021
|
Requisite information has been upload
|
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
08/07/2021
|
Requisite information has been upload
|
|