TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/117213/2020              (ii). Name of Project for which Forest Land is required : Construction of link road near Bachhod Railway Station from Ateli disty to Bhilwara road in district Mahendergarh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of link road near Bachhod Railway Station from Ateli disty to Bhilwara road under forest division and district Mahendergarh Haryana. The project approved by DCE DFCCIL Jaipur vide ltr no 12 dated 07-01-2020.              (iv). File no. : 9706              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.27
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/ROAD/117213/202027/12/202030/12/2020   04/01/2021   05/01/2021   25/01/2021 Mahendergarh :01/02/2021South Circle Gurgaon:
  01/02/2021 (Mahendergarh)

Haryana:
09/02/2021
Haryana:
24/02/2021
25/02/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .