TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/RAIL/146848/2021              (ii). Name of Project for which Forest Land is required : Construction of Halt Station/Platfor on Delhi Rewari Sadulpur Railway line at chainage 101.3 village Siha Tehsil and district Rewari Haryana              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Halt Station/Platfor on Delhi Rewari Sadulpur Railway line at chainage 101.3 village Siha Tehsil and district Rewari Haryana              (iv). File no. : D-III-10143              (v). State : Haryana              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.2538
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/RAIL/146848/202122/09/202129/09/2021   09/10/2021   12/10/2021   19/10/2021 Rewari :25/10/2021South Circle Gurgaon:
  18/11/2021 (Rewari)

Haryana:
03/12/2021
Haryana:
13/12/2021
14/12/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Rewari) on:27/10/2021  
Replied by UA on :12/11/2021  
NOTE:- Stage-I Approval accorded by : State Government .