| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Charkhi Dadri)
|
EDS
|
User Agency (bonddivision1@gmail.com)
|
19/08/2020
|
Requisite information has been uploaded
|
|
|
2
|
User Agency (bonddivision1@gmail.com)
|
REPLY
|
DFO (Charkhi Dadri)
|
19/08/2020
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
02/09/2020
|
Case down
|
|
|
4
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
04/09/2020
|
Case down
|
|
|
5
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
07/09/2020
|
Requisite information has been uploaded.
|
|
|
6
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
18/09/2020
|
Requisite information has been uploaded.
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
01/10/2020
|
Upload correct Land suitability certificate
|
|
|
8
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
01/10/2020
|
Upload correct Land suitability certificate
|
|
|
9
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
27/10/2020
|
correction have been made as per the instruction received.
|
|
|
10
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
28/10/2020
|
correction have been made as per the instruction received.
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
29/10/2020
|
1.ECO class shown as ECO-I instead of ECO-3 2. Marking list of trees not uploaded 3. Upload all checklists/undertakings countersigned by DFO not uploaded 4. Upload Land suitability certificate
|
|
|
12
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
29/10/2020
|
1.ECO class shown as ECO-I instead of ECO-3 2. Marking list of trees not uploaded 3. Upload all checklists/undertakings countersigned by DFO not uploaded 4. Upload Land suitability certificate
|
|
|
13
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
29/10/2020
|
Requistion has been uploaded
|
|
|
14
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
29/10/2020
|
Requistion has been uploaded
|
|
|
15
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
02/11/2020
|
Requistion has been uploaded
|
|