TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Pipeline/43175/2019              (ii). Name of Project for which Forest Land is required : for R.C.C. Pipe, Inlet Channel of 350mm Pipe on Pillar at Barsola Minor to Bhongra Village in Distt. Jind (HR).              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This is a proposal of Diversion of forest Land of 0.24129Ha. for R.C.C. Pipe, Inlet Channel of 350mm Pipe on Pillar at Barsola Minor to Bhongra Village in Distt. Jind (HR).              (iv). File no. : 9349              (v). State : Haryana              (vi). Category of the Project : Pipeline              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.24129
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/Pipeline/43175/201910/03/202017/03/2020   01/05/2020   07/05/2020   07/05/2020 Jind :12/05/2020West Circle Hissar:
  02/06/2020 (Jind)

Haryana:
18/06/2020
Haryana:
09/03/2021
10/03/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Haryana) on:26/06/2020  
Replied by Circle(West Circle Hissar) on:06/07/2020  
Query raised by Nodal Officer (Haryana) on:29/07/2020  
Replied by Circle(West Circle Hissar) on:11/08/2020  
Query raised by Nodal Officer (Haryana) on:31/10/2020  
Replied by Circle(West Circle Hissar) on:03/11/2020  
Query raised by Nodal Officer (Haryana) on:20/01/2021  
Replied by Circle(West Circle Hissar) on:28/01/2021  
Query raised by Circle (West Circle Hissar) on:26/06/2020  
Replied by DFO (Jind) on:06/07/2020  
Query raised by Circle (West Circle Hissar) on:29/07/2020  
Replied by DFO (Jind) on:10/08/2020  
Query raised by Circle (West Circle Hissar) on:02/11/2020  
Replied by DFO (Jind) on:02/11/2020  
Query raised by Circle (West Circle Hissar) on:25/01/2021  
Replied by DFO (Jind) on:27/01/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
   Query raised by State Government (Haryana) on:23/01/2024  
Query raised by Nodal Officer on:30/01/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government for verifying Compliance of Conditions .