TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Others/39588/2019              (ii). Name of Project for which Forest Land is required : construction of Sewerage line from Uchana-Dhollgarh road Near railway crossing to Karnal-Kachwa road SH-9              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.826 Hec. of forest land for construction of Sewerage line from Uchana-Dhollgarh road (Near railway crossing) to Karnal-Kachwa road SH-9 under Division & Distt. Karnal, (Haryana).              (iv). File no. : 8857              (v). State : Haryana              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.826
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/Others/39588/201927/03/201901/04/2019   18/04/2019   29/04/2019   28/06/2019 Karnal :01/07/2019Central Circle Rohtak:
  02/07/2019 (Karnal)

Haryana:
02/07/2019
Haryana:
11/07/2019
12/07/2019
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .