TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Others/26504/2017              (ii). Name of Project for which Forest Land is required : Laying of HDPE Pipe Line Kaluwas STP to Nasiyaji STP Rewari Twol              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of HDPE pipe line from Kaluwas STP to Nasiyaji STP. Providing effluent carrier from STP of Rewari Town to Sabi river.The project already technically approved by Engineer in Chief Haryana Public Health Engineering department Panchkula letter no. 25240 dated 22-03-2017. Under Forest division a              (iv). File no. : D-III-8152              (v). State : Haryana              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.21
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/Others/26504/201702/06/201730/08/2017  13/06/2017   04/09/2017  10/08/2017   05/09/2017   27/10/201727/10/2017 Rewari :03/11/2017South Circle Gurgaon:
  07/11/2017 (Rewari)

Haryana:
09/11/2017
Haryana:
27/12/2017
22/11/2017
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)