TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Others/17315/2015              (ii). Name of Project for which Forest Land is required : for providing water supply to Nalhar Medical College              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.28 ha of forest land for providing water supply to Nalhar Medical College, Nuh Town, Farrukh Nagar, Town, Pataudi Town and surrounding 17 No. villages of Distt Mewat (construction of water storage reservoir)              (iv). State : Haryana              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.28
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/Others/17315/201530/12/201511/03/2016  01/02/2016  25/01/2016  13/01/2016   29/04/2016  11/02/2016  27/01/2016  21/01/2016   18/02/2016   09/03/2016 Mewat :02/05/2016South Circle Gurgaon:
  19/05/2016 (Mewat)

Haryana:
01/06/2016
Haryana:
14/06/2016
Chandigarh:
14/06/2016
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:27/06/2016  
Query raised by State Government (Haryana) on:29/03/2017  
Replied by Nodal Officer (Haryana) on:23/11/2019  
Query raised by State Government (Haryana) on:24/06/2022  
Query raised by Nodal Officer (Haryana) on:29/03/2017  
Replied by Circle(South Circle Gurgaon) on:30/01/2018  
Query raised by Nodal Officer (Haryana) on:24/06/2022  
Replied by Circle(South Circle Gurgaon) on:05/07/2022  
Query raised by Circle (South Circle Gurgaon) on:30/03/2017  
Replied by DFO (Mewat) on:30/01/2018  
Query raised by Circle (South Circle Gurgaon) on:27/06/2022  
Replied by DFO (Mewat) on:05/07/2022  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .