TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Others/150474/2021              (ii). Name of Project for which Forest Land is required : IOCLtd. at village Lohani Distt. Bhiwani              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.0019 ha. of forest land for construction of Open drain in addition to 0.081 ha. forest land already diverted for access to Retail Outlet of IOCLtd. at village Lohani Distt. Bhiwani              (iv). File no. : 9-HRB151-2022-CHA              (v). State : Haryana              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0019
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/Others/150474/202124/12/202131/12/2021   31/12/2021   24/12/2021   31/12/2021 Bhiwani(West Circle Hissar) :31/12/2021West Circle Hissar:
  18/01/2022 (Bhiwani(West Circle Hissar))

Haryana:
31/01/2022
Haryana:
30/06/2022
Chandigarh:
30/06/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:29/07/2022  
Query raised by State Government (Haryana) on:26/08/2022  
Replied by Nodal Officer (Haryana) on:20/12/2024  
Query raised by Nodal Officer (Haryana) on:09/03/2022  
Replied by Circle(West Circle Hissar) on:30/03/2022  
Query raised by Nodal Officer (Haryana) on:20/05/2022  
Replied by Circle(West Circle Hissar) on:13/06/2022  
Query raised by Nodal Officer (Haryana) on:26/08/2022  
Replied by Circle(West Circle Hissar) on:15/09/2022  
Query raised by Nodal Officer (Haryana) on:31/10/2022  
Replied by Circle(West Circle Hissar) on:17/11/2022  
Query raised by Nodal Officer (Haryana) on:09/12/2022  
Replied by Circle(West Circle Hissar) on:21/12/2022  
Query raised by Nodal Officer (Haryana) on:25/01/2023  
Replied by Circle(West Circle Hissar) on:22/11/2023  
Query raised by Nodal Officer (Haryana) on:06/03/2024  
Replied by Circle(West Circle Hissar) on:21/03/2024  
Query raised by Nodal Officer (Haryana) on:15/04/2024  
Replied by Circle(West Circle Hissar) on:03/05/2024  
Query raised by Nodal Officer (Haryana) on:15/10/2024  
Replied by Circle(West Circle Hissar) on:18/10/2024  
Query raised by Circle (West Circle Hissar) on:18/01/2022  
Replied by DFO (Bhiwani(West Circle Hissar)) on:20/01/2022  
Query raised by Circle (West Circle Hissar) on:21/01/2022  
Replied by DFO (Bhiwani(West Circle Hissar)) on:29/01/2022  
Query raised by Circle (West Circle Hissar) on:09/03/2022  
Replied by DFO (Bhiwani(West Circle Hissar)) on:29/03/2022  
Query raised by Circle (West Circle Hissar) on:26/08/2022  
Replied by DFO (Bhiwani(West Circle Hissar)) on:15/09/2022  
Query raised by Circle (West Circle Hissar) on:02/11/2022  
Replied by DFO (Bhiwani(West Circle Hissar)) on:17/11/2022  
Query raised by Circle (West Circle Hissar) on:12/12/2022  
Replied by DFO (Bhiwani(West Circle Hissar)) on:21/12/2022  
Query raised by Circle (West Circle Hissar) on:27/01/2023  
Replied by DFO (Bhiwani(West Circle Hissar)) on:02/03/2023  
Query raised by Circle (West Circle Hissar) on:07/03/2024  
Replied by DFO (Bhiwani(West Circle Hissar)) on:19/03/2024  
Query raised by Circle (West Circle Hissar) on:16/10/2024  
Replied by DFO (Bhiwani(West Circle Hissar)) on:18/10/2024  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .