TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/OFC/154299/2022              (ii). Name of Project for which Forest Land is required : LAYING OF UNDERGOUND OFC BY JIO DIGITAL FIBRE PRIVATE LIMITED IN SIRS DIVION              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : TO LAYING UNDERGROUND OFC BY JIO DIGITAL FIBRE PRIVATE LIMITED IN SIRSA FOREST & DISTRICT. TOTAL LENGTH WOULD BE REQUIRED 0.945 HECTARE (2100 METERS) (FSA SIRS 0111 & 0115)              (iv). File no. : 4997-ft-2-2023/7524              (v). State : Haryana              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.945
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/OFC/154299/202210/04/202217/05/2022   23/05/2022   27/05/2022   02/06/2022 Sirsa :02/06/2022West Circle Hissar:
  01/10/2022 (Sirsa)

Haryana:
06/10/2022
Haryana:
29/09/2023
20/11/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Haryana) on:04/05/2023  
Replied by Circle(West Circle Hissar) on:06/09/2023  
Query raised by Circle (West Circle Hissar) on:04/05/2023  
Replied by DFO (Sirsa) on:06/09/2023  
Query raised by DFO (Sirsa) on:04/05/2023  
Replied by UA on :11/07/2023  
Query raised by DFO (Sirsa) on:20/07/2023  
Replied by UA on :20/07/2023  
Query raised by DFO (Sirsa) on:08/08/2023  
Replied by UA on :23/08/2023  
Query raised by DFO (Sirsa) on:04/09/2023  
Replied by UA on :06/09/2023  
NOTE:- Stage-I Approval accorded by : State Government .