TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/OFC/142408/2021              (ii). Name of Project for which Forest Land is required : Laying of Underground OFC in Sirsa Division by Jio digital Fibre Private limited              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : LAYING OF UNDERGROUND OFC BY JIO DIGITAL FIBRE PRIVATE LIMITED IN SIRSA DIVISION. (FSA SIRS 0112). TOTAL LENGHT 335 METERS (0.0151 HECTARE)              (iv). File no. : 10164              (v). State : Haryana              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0151
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HR/OFC/142408/202120/05/202108/06/2021   10/06/2021   15/06/2021   18/11/2021 Sirsa :22/11/2021West Circle Hissar:
  06/12/2021 (Sirsa)

Haryana:
14/12/2021
Haryana:
21/12/2021
22/12/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .