TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/OFC/123282/2021              (ii). Name of Project for which Forest Land is required : Laying of Underground OFC by Jio Digital Fibre Pvt Limtied in Panipat Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Underground OFC by Jio Digital Fibre Private Limited in Panipat Forest Division. (FSA PNPT - 0131). Total Land would be required 344 meters (0.0155 Hectare)              (iv). State : Haryana              (v). Category of the Project : Optical Fibre Cable              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0155
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/OFC/123282/202117/02/202126/02/2021   26/02/2021   02/03/2021   18/06/2021 Panipat :21/06/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Panipat) on:25/08/2021  
Replied by UA on :17/12/2021  
Query raised by DFO (Panipat) on:22/12/2021  
Replied by UA on :06/01/2022  
Query raised by DFO (Panipat) on:10/01/2022  
Replied by UA on :15/09/2023  
Query raised by DFO (Panipat) on:26/10/2023  
Replied by UA on :14/03/2024  
Query raised by DFO (Panipat) on:27/03/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .