| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Charkhi Dadri)
|
EDS
|
User Agency (bonddivision1@gmail.com)
|
19/08/2020
|
Requisite information has been uploaded
|
|
|
2
|
User Agency (bonddivision1@gmail.com)
|
REPLY
|
DFO (Charkhi Dadri)
|
19/08/2020
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
07/09/2020
|
Case down
|
|
|
4
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
09/09/2020
|
Case down
|
|
|
5
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
14/09/2020
|
Requisite information has been uploaded.
|
|
|
6
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
18/09/2020
|
Requisite information has been uploaded.
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
02/10/2020
|
1.ECO class shown as ECO-I instead of ECO-3
2. Marking list of trees not uploaded
3. Upload all checklists/undertakings countersigned by DFO not uploaded
4. Upload Land suitability certificate
|
|
|
8
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
05/10/2020
|
1.ECO class shown as ECO-I instead of ECO-3 2. Marking list of trees not uploaded 3. Upload all checklists/undertakings countersigned by DFO not uploaded 4. Upload Land suitability certificate
|
|
|
9
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
27/10/2020
|
Requisite reply has been uploaded.
|
|
|
10
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
28/10/2020
|
Requisite reply has been uploaded.
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
29/10/2020
|
1.ECO class shown as ECO-I instead of ECO-3 2. Marking list of trees not uploaded 3. Upload all checklists/undertakings countersigned by DFO not uploaded 4. Upload Land suitability certificate
|
|
|
12
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
29/10/2020
|
1.ECO class shown as ECO-I instead of ECO-3 2. Marking list of trees not uploaded 3. Upload all checklists/undertakings countersigned by DFO not uploaded 4. Upload Land suitability certificate
|
|
|
13
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
29/10/2020
|
Requisition has been uploaded
|
|
|
14
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
02/11/2020
|
Requisition has been uploaded
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
02/11/2020
|
KML file of CA site is not getting downloaded. Kindly upload KML file of CA site properly.
|
|
|
16
|
CF (West Circle Hissar)
|
EDS
|
DFO (Charkhi Dadri)
|
03/11/2020
|
KML file of CA site is not getting downloaded. Kindly upload KML file of CA site properly.
|
|
|
17
|
DFO (Charkhi Dadri)
|
REPLY
|
CF (West Circle Hissar)
|
19/11/2020
|
The Requisite information has been uploaded.
|
|
|
18
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
25/11/2020
|
The Requisite information has been uploaded.
|
|