  (i). Proposal No. : FP/HR/Approach/49074/2020              (ii). Name of Project for which Forest Land is required : Diversion of 0.01463 Ha. of Forest Land for Biomass Power Plant in Dera Dillu Ram, Link Road VPO Kangthali in Kaithal District, under Forest Division & Distt. Kaithal, Haryana.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.01463 Ha. of Forest Land for Biomass Power Plant in Dera Dillu Ram, Link Road VPO Kangthali in Kaithal District, under Forest Division & Distt. Kaithal, Haryana.              (iv). File no. : 9-HRB008-2021-CHA              (v). State : Haryana              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.01463
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HR/Approach/49074/202028/08/202027/10/2020  20/10/2020  18/09/2020   09/11/2020  20/10/2020  01/10/2020   22/10/2020   23/10/2020 Kaithal :16/11/2020North Circle Panchkula:
  10/12/2020 (Kaithal)

Haryana:
30/12/2020
Haryana:
14/01/2021
Chandigarh:
14/01/2021
09/02/2021
By :Regional Office
Haryana
15/07/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:27/07/2022  
Query raised by State Government (Haryana) on:08/02/2023  
Query raised by Nodal Officer on:02/05/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .