Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
05/04/2018
|
eds
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
17/04/2018
|
upload information sought by GoI
|
|
3
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
17/04/2018
|
upload information sought by GoI
|
|
4
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
17/04/2018
|
Query attached
|
|
5
|
DFO (Gurgaon)
|
EDS
|
User Agency (jasminebuildmart@gmail.com)
|
14/08/2018
|
Query Attached
|
|
6
|
User Agency (jasminebuildmart@gmail.com)
|
REPLY
|
DFO (Gurgaon)
|
09/05/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
01/10/2019
|
Query attached.
|
|
8
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
01/10/2019
|
Query attached
|
|
9
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
26/11/2019
|
upload information sought vide attached letter
|
|
10
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
27/11/2019
|
upload information sought vide attached letter
|
|
11
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
10/07/2020
|
Essential details and revised CA scheme already sent to CCF(FCA) Panchkula vide letter no 198 dt 26.06.2020
|
|
12
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
14/07/2020
|
Essential details and revised CA scheme already sent to CCF(FCA) Panchkula vide dfo letter no 198 dt 26.06.2020
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
20/07/2020
|
Reply sent
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
20/07/2020
|
Reply sent
|
|