Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kurukshetra)
|
EDS
|
User Agency (kamitkumarkamit25@gmail.com)
|
05/01/2023
|
Please update information
|
|
2
|
User Agency (kamitkumarkamit25@gmail.com)
|
REPLY
|
DFO (Kurukshetra)
|
07/01/2023
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
06/04/2023
|
case down
|
|
4
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kurukshetra)
|
12/04/2023
|
send the report
|
|
5
|
DFO (Kurukshetra)
|
EDS
|
User Agency (kamitkumarkamit25@gmail.com)
|
12/04/2023
|
Please update information as per directions received
|
|
6
|
User Agency (kamitkumarkamit25@gmail.com)
|
REPLY
|
DFO (Kurukshetra)
|
11/05/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Kurukshetra)
|
REPLY
|
CF (North Circle Panchkula)
|
08/06/2023
|
The correction have been made as per the instruction received
|
|
8
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
12/06/2023
|
report updated
|
|
9
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
26/06/2023
|
1. Marking list of trees to be felled has not been uploaded.
2. Scientific names of some trees species have not been uploaded. The same have been shown under Misc.
3. In specific recommendation letter of DFO Part-II, density of vegetation also needs to be corrected.
4. In addition, CA scheme needs to be revised as per latest cost norms issued by this office letter dated 15.05.2023
|
|
10
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kurukshetra)
|
04/07/2023
|
1. Marking list of trees to be felled has not been uploaded. 2. Scientific names of some trees species have not been uploaded. The same have been shown under Misc. 3. In specific recommendation letter of DFO Part-II, density of vegetation also needs to be corrected. 4. In addition, CA scheme needs to be revised as per latest cost norms issued by this office letter dated 15.05.2023
|
|
11
|
DFO (Kurukshetra)
|
REPLY
|
CF (North Circle Panchkula)
|
12/07/2023
|
The correction have been made as per the instruction received
|
|
12
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
12/07/2023
|
case updated by dfo
|
|
13
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
04/08/2023
|
1. Scientific names of some trees species have not been uploaded. The same are still shown under Misc.
2. In specific recommendation letter of DFO Part-II, density of vegetation also needs to be corrected.
3. In addition, in CA scheme, fencing charges are taken at 2 lac per RKM which are not as per latest cost norms issued by this office letter dated 15.05.2023.
|
|
14
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kurukshetra)
|
10/08/2023
|
1. Scientific names of some trees species have not been uploaded. The same are still shown under Misc. 2. In specific recommendation letter of DFO Part-II, density of vegetation also needs to be corrected. 3. In addition, in CA scheme, fencing charges are taken at 2 lac per RKM which are not as per latest cost norms issued by this office letter dated 15.05.2023.
|
|
15
|
DFO (Kurukshetra)
|
REPLY
|
CF (North Circle Panchkula)
|
28/08/2023
|
The correction have been made as per the instruction received
|
|
16
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
29/08/2023
|
The correction have been made as per the instruction received
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
28/11/2023
|
eds
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
01/12/2023
|
EDS Raised by IRO MOEF
|
|
19
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
01/12/2023
|
Case down - EDS by IRO
|
|
20
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kurukshetra)
|
05/12/2023
|
update the case as per instuctions
|
|
21
|
DFO (Kurukshetra)
|
EDS
|
User Agency (kamitkumarkamit25@gmail.com)
|
11/12/2023
|
Please update information as per directions received
|
|
22
|
User Agency (kamitkumarkamit25@gmail.com)
|
REPLY
|
DFO (Kurukshetra)
|
29/04/2024
|
The correction have been made as per the instruction received
|
|