Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
17/10/2022
|
Case down
|
|
2
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
17/10/2022
|
Case down
|
|
3
|
DFO (Hisar)
|
EDS
|
User Agency (dcmhsr.2021@gmail.com)
|
18/10/2022
|
EDS Raised
|
|
4
|
User Agency (dcmhsr.2021@gmail.com)
|
REPLY
|
DFO (Hisar)
|
26/10/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
09/11/2022
|
EDS Removed
|
|
6
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
14/11/2022
|
EDS Removed
|
|
7
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
02/01/2023
|
Case Down
|
|
8
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
02/01/2023
|
Case Down
|
|
9
|
DFO (Hisar)
|
EDS
|
User Agency (dcmhsr.2021@gmail.com)
|
02/01/2023
|
EDS Raised
|
|
10
|
User Agency (dcmhsr.2021@gmail.com)
|
REPLY
|
DFO (Hisar)
|
02/01/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Hisar)
|
EDS
|
User Agency (dcmhsr.2021@gmail.com)
|
04/01/2023
|
Plz upload employment undertaking
|
|
12
|
User Agency (dcmhsr.2021@gmail.com)
|
REPLY
|
DFO (Hisar)
|
04/01/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
04/01/2023
|
EDS Removed
|
|
14
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
04/01/2023
|
EDS Removed by DFO
|
|
15
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
06/01/2023
|
Case Down
|
|
16
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
09/01/2023
|
Case Down
|
|
17
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
11/01/2023
|
EDS Already Removed
|
|
18
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
11/01/2023
|
EDS Already Removed by DFO
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
15/02/2023
|
in online part II column no 16 recommended letter by DFO density is not match with online part ii column 4 upload upload correct recommendation letter
|
|
20
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
21/02/2023
|
In online part II column no 16 recommended letter by DFO density is not match with online part ii column 4 upload upload correct recommendation letter.
|
|
21
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
21/02/2023
|
In online part II column no 16 recommended letter by DFO density is not match with online part ii column 4 upload upload correct recommendation letter.
|
|
22
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
22/02/2023
|
In Online Part II column no. 16 revised recommendation letter by DFO is not uploaded. Revised recommendation uploaded in Additional Documents in Part II.
|
|
23
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
22/02/2023
|
In Online Part II column no. 16 revised recommendation letter by DFO is not uploaded. Revised recommendation uploaded in Additional Documents in Part II.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
09/03/2023
|
The correction have been made as per the instruction received and part-II uploaded in Part-II Additional Detail S.No. 5
|
|
25
|
State secretary
|
EDS
|
Nodal Officer
|
15/03/2023
|
Pls Upload Revise Part II recommendation letter in coloumn no 16
|
|
26
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
15/03/2023
|
Upload Revise Part II recommendation letter in coloumn no 16 density of vegetation is not match column no 4 i i.e 0.1 . Update correct density of vegetation in recommendation letter.
|
|
27
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
15/03/2023
|
Upload Revise Part II recommendation letter in coloumn no 16 density of vegetation is not match column no 4 i i.e 0.1 . Update correct density of vegetation in recommendation letter.
|
|
28
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
20/03/2023
|
EDS Removed
|
|
29
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
20/03/2023
|
EDS Removed by DFO
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
28/03/2023
|
Correction have been done in Part II recommendation letter by DFO
|
|
31
|
State secretary
|
EDS
|
Nodal Officer
|
13/04/2023
|
in this context you are requested to clarify Whether SMC charges is applicable or not in this proposal
2. Upload DGPS map of CA site with Fully Scan with scale of longitude
|
|
32
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
13/04/2023
|
1. In this context you are requested to clarify Whether SMC charges is applicable or not in this proposal
2. Upload DGPS map of CA site with Fully Scan with scale of longitude
|
|
33
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
13/04/2023
|
1. In this context you are requested to clarify Whether SMC charges is applicable or not in this proposal 2. Upload DGPS map of CA site with Fully Scan with scale of longitude
|
|
34
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
19/04/2023
|
Raised EDS Removed
|
|
35
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
19/04/2023
|
Raised EDS Removed by DFO
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
20/04/2023
|
SMC charges removed from CA scheme.DGPS map uploaded
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
25/05/2023
|
eds
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
29/05/2023
|
case down
|
|
39
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
29/05/2023
|
Case down - EDS RO
|
|
40
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
29/05/2023
|
Case down - EDS RO
|
|
41
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
15/06/2023
|
RAISED EDS REMOVED
|
|
42
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
16/06/2023
|
RAISED EDS REMOVED
|
|
43
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
07/07/2023
|
1. CA Area has been calculated mentioned wrongly in CA Scheme and in Part-II online as well. It should be 0.116 ha instead of mentioned 0.10 ha.
In CA scheme area is still 0.10 ha. which needs to be corrected.
2. The perimeter of the KML uploaded as CA site is approx 4.81 km for 5 patches and in CA scheme 0.46 rkm has been taken as barbed wire fencing. Thus the area dedicated for the plantation of the desired number of plants needs to be marked as KML OR the details of other plantations if any undertaken in the proposed CA site viz. Scheme under which plantation raised Year of Plantation Number of Plants and Species is required to be submitted.
CA site KML needs to be revised as it falls over the canal.
|
|
44
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
07/07/2023
|
1. CA Area has been calculated mentioned wrongly in CA Scheme and in Part-II online as well. It should be 0.116 ha instead of mentioned 0.10 ha. In CA scheme area is still 0.10 ha. which needs to be corrected. 2. The perimeter of the KML uploaded as CA site is approx 4.81 km for 5 patches and in CA scheme 0.46 rkm has been taken as barbed wire fencing. Thus the area dedicated for the plantation of the desired number of plants needs to be marked as KML OR the details of other plantations if any undertaken in the proposed CA site viz. Scheme under which plantation raised Year of Plantation Number of Plants and Species is required to be submitted. CA site KML needs to be revised as it falls over the canal.
|
|
45
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
24/07/2023
|
EDS Removal Letter
|
|
46
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
25/07/2023
|
EDS Removal Letter
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
03/08/2023
|
EDS Reply
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
03/08/2023
|
EDS Resolved case sent to IRO MOEF
|
|