Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kullu)
|
EDS
|
User Agency (esdkatrain@gmail.com)
|
31/12/2019
|
Please send the four numbers of proposal folders complete in all respect to this office at the earliest.
|
|
2
|
User Agency (esdkatrain@gmail.com)
|
REPLY
|
DFO (Kullu)
|
13/02/2020
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
02/03/2020
|
EDS
|
|
4
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
04/03/2020
|
EDS
|
|
5
|
DFO (Kullu)
|
EDS
|
User Agency (esdkatrain@gmail.com)
|
04/03/2020
|
Please attend the shortcomings as raised by Nodal Officer
|
|
6
|
User Agency (esdkatrain@gmail.com)
|
REPLY
|
DFO (Kullu)
|
09/03/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Kullu)
|
EDS
|
User Agency (esdkatrain@gmail.com)
|
11/03/2020
|
The point No.3 i.e. regarding employment generation has not been attended. It may please be attended at the earliest please.
|
|
8
|
User Agency (esdkatrain@gmail.com)
|
REPLY
|
DFO (Kullu)
|
18/03/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
18/03/2020
|
The correction have been made as per the instruction received
|
|
10
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
20/03/2020
|
EDS attended
|
|
11
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
16/05/2020
|
Hard copy of the reply have not been received in this office.
|
|
12
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
18/05/2020
|
Hard copy of the reply a/w enclosures has already been sent on dated 21.03.2020. However, copy of the same is attached.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
26/05/2020
|
Comments of CWLW is also required to be obtained.
|
|
14
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
28/05/2020
|
Comments of CWLW are also required to be obtained.
|
|
15
|
DFO (Kullu)
|
EDS
|
User Agency (esdkatrain@gmail.com)
|
29/05/2020
|
Comments of CWLW are also required to be obtained.
|
|
16
|
User Agency (esdkatrain@gmail.com)
|
REPLY
|
DFO (Kullu)
|
01/06/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
20/06/2020
|
Sr. Executive Engineer, Electrical Division, HPSEBL, Manali has reported that matter regarding issuing of comments of Chief Wild Life Warden has already been taken up Pr,CCF (WL), HP. Further , he has informed that matter has also been discussed in the office of Pr,CCF (WL) ,HP and they have informed that comments of Chief Wild life Warden will be submitted directly to Nodal Officer-cum-APCCF (FCA) O/o Pr,CCF (HoFF) , HP
|
|
18
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
20/06/2020
|
Sr. Executive Engineer, Electrical Division, HPSEBL, Manali has reported that matter regarding issuing of comments of Chief Wild Life Warden has already been taken up Pr,CCF (WL), HP. Further , he has informed that matter has also been discussed in the office of Pr,CCF (WL) ,HP and they have informed that comments of Chief Wild life Warden will be submitted directly to Nodal Officer-cum-APCCF (FCA) O/o Pr,CCF (HoFF) , HP
|
|
19
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
24/06/2020
|
EDS attended
|
|
20
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
04/07/2020
|
Comments of CWLW is also required to be obtained and uploaded in part II against additional documents.
|
|
21
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
04/07/2020
|
Comments of CWLW is also required to be obtained and uploaded in part II against additional documents.
|
|
22
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
10/07/2020
|
Comments of CWLW is has been uploaded in part II against additional documents.
|
|
23
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
10/07/2020
|
As desired, Comments of Chief Wild Life Warden has been uploaded in Part-11 by DFO against additional documents please.
|
|