TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/TRANS/130156/2021              (ii). Name of Project for which Forest Land is required : Construction of LILO from 400KV D/C Transmission line Lahal to Rajera at Tower no 8 to Pot Head yard for Evacuation of Power of JSW ENERGY (KUTEHR)LTD KUTEHR HEP 3X80 MW Vill. Machhettar Post Chanhota              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of LILO from 400KV D/C Transmission line Lahal to Rajera at Tower no 8 to Pot Head yard for Evacuation of Power of JSW ENERGY (KUTEHR)LTD KUTEHR HEP 3X80 MW Vill. Machhettar Post Chanhota Teh. Bharmour Distt. Chamba. (H.P.)              (iv). File no. : 8-47/2011-FC Pt.              (v). State : Himachal Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.7904
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HP/TRANS/130156/202113/03/202106/04/2021  31/03/2021  26/03/2021   08/04/2021  01/04/2021  30/03/2021   23/04/2021   27/04/2021 Bharmour :28/04/2021Chamba:
  21/06/2021 (Bharmour)

Himachal Pradesh:
16/07/2021
Himachal Pradesh:
29/11/2021
03/01/2022
HO Linked Date:
13/03/2023
05/07/2023
By :Head Office
Himachal Pradesh
22/02/2024
15/03/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 14/03/2023  
Replied by State Government (Himachal Pradesh) on:21/03/2023  
Query raised by MoEFCC,New Delhi on 20/04/2023  
Replied by State Government (Himachal Pradesh) on:12/05/2023  
Query raised by State Government (Himachal Pradesh) on:14/03/2023  
Replied by Nodal Officer (Himachal Pradesh) on:21/03/2023  
Query raised by State Government (Himachal Pradesh) on:20/04/2023  
Replied by Nodal Officer (Himachal Pradesh) on:12/05/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:22/07/2021  
Replied by Circle(Chamba) on:23/07/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:07/08/2021  
Replied by Circle(Chamba) on:01/09/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:21/09/2021  
Replied by Circle(Chamba) on:25/11/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:15/03/2023  
Replied by Circle(Chamba) on:18/03/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:20/04/2023  
Replied by Circle(Chamba) on:12/05/2023  
Query raised by Circle (Chamba) on:09/08/2021  
Replied by DFO (Bharmour) on:25/08/2021  
Query raised by Circle (Chamba) on:22/09/2021  
Replied by DFO (Bharmour) on:25/11/2021  
Query raised by Circle (Chamba) on:25/11/2021  
Replied by DFO (Bharmour) on:25/11/2021  
Query raised by Circle (Chamba) on:15/03/2023  
Replied by DFO (Bharmour) on:18/03/2023  
Query raised by Circle (Chamba) on:24/04/2023  
Replied by DFO (Bharmour) on:12/05/2023  
Query raised by DFO (Bharmour) on:29/04/2021  
Replied by UA on :16/06/2021  
Query raised by DFO (Bharmour) on:10/08/2021  
Replied by UA on :25/08/2021  
Query raised by DFO (Bharmour) on:29/09/2021  
Replied by UA on :25/11/2021  
Query raised by DFO (Bharmour) on:16/03/2023  
Replied by UA on :17/03/2023  
Query raised by DFO (Bharmour) on:10/05/2023  
Replied by UA on :12/05/2023  
NOTE:- Stage-II Approval accorded by : Head Office .