Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
07/02/2023
|
EDS
|
|
2
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
27/03/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
04/05/2023
|
EDS
|
|
4
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
10/05/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
03/06/2023
|
EDS
|
|
6
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
06/06/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
07/06/2023
|
Hard Copy of proposal not received please send the same.
|
|
8
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
07/06/2023
|
The correction have been made as per the instruction received
|
|
9
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
09/08/2023
|
EDS
|
|
10
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
10/08/2023
|
EDS
|
|
11
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
21/08/2023
|
EDS
|
|
12
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
25/08/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
31/08/2023
|
The reply is not submitted point No. 3
|
|
14
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
31/08/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
06/09/2023
|
Observations as raised by CCF Bilaspur has been attended to vide this office letter No. 5447 dated 06.09.2023
|
|
16
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
11/09/2023
|
EDS attended.
|
|
17
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
12/09/2023
|
As per the component wise breakup three roads has still shown whereas proposal is prepared for one road further the private land has not been marked in the KML file. The bridge has been proposed hence component of bridge may be shown in Online part I.
|
|
18
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
13/09/2023
|
As per the component wise breakup three roads has still shown whereas proposal is prepared for one road further the private land has not been marked in the KML file. The bridge has been proposed hence component of bridge may be shown in Online part I.
|
|
19
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
14/09/2023
|
As per the component wise breakup three roads has still shown whereas proposal is prepared for one road further the private land has not been marked in the KML file. The bridge has been proposed hence component of bridge may be shown in Online part I.
|
|
20
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
15/09/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
16/09/2023
|
In this behalf, user agency has submitted that only one road has been proposed but there are three beneficiary villages namely Bholi, Bhatoli & Gassour. Necessary correction has been made in component-wise breakup through online part-I by user agency. This road will pass through Ali Khad for which 55 meter span PSC Box Girder Bridge has been proposed to be constructed. Both side approaches of this bridge will be constructed in Private land, which has already been depicted on the KML file as yellow colour. This is for favour of information and further necessary action at your end please.
|
|
22
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
19/09/2023
|
In this behalf, user agency has submitted that only one road has been proposed but there are three beneficiary villages namely Bholi, Bhatoli & Gassour. Necessary correction has been made in component-wise breakup through online part-I by user agency. This road will pass through Ali Khad for which 55 meter span PSC Box Girder Bridge has been proposed to be constructed. Both side approaches of this bridge will be constructed in Private land, which has already been depicted on the KML file as yellow colour. This is for favour of information and further necessary action at your end please.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
20/09/2023
|
As per the component wise breakup three roads has still shown whereas proposal is prepared for one road further the private land has not been marked in the KML file. The bridge has been proposed hence component of bridge may be shown in Online part I.
|
|
24
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
21/09/2023
|
As per the component wise breakup three roads has still shown whereas proposal is prepared for one road further the private land has not been marked in the KML file. The bridge has been proposed hence component of bridge may be shown in Online part I.
|
|
25
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
21/09/2023
|
As per the component wise breakup three roads has still shown whereas proposal is prepared for one road further the private land has not been marked in the KML file. The bridge has been proposed hence component of bridge may be shown in Online part I.
|
|
26
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
27/09/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
04/10/2023
|
The revised KML file uploaded and necessary correction has been made in component- wise breakup through online by the user agency.
|
|
28
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
05/10/2023
|
The revised KML file uploaded and necessary correction has been made in component- wise breakup through online by the user agency.
|
|
29
|
State secretary
|
EDS
|
Nodal Officer
|
02/12/2023
|
Kindly attend the EDS
|
|
30
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
04/12/2023
|
EDS
|
|
31
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
05/12/2023
|
EDS
|
|
32
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
12/12/2023
|
EDS
|
|
33
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
21/12/2023
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
23/12/2023
|
Observations as raised by CCF Bilaspur has been attended to vide this office letter No. 9664 dated 22.12.2023
|
|
35
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
08/01/2024
|
EDS attended.
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
09/01/2024
|
Complete reply is submitted
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
04/10/2024
|
EDS
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
07/10/2024
|
EDS
|
|
39
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
07/10/2024
|
EDS
|
|
40
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
08/10/2024
|
EDS
|
|
41
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
14/10/2024
|
EDS
|
|
42
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
20/11/2024
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
04/12/2024
|
Observations as raised by CCF Bilaspur has been attended to vide this office letter No. 7754 dated 03.12.2024
|
|
44
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
07/12/2024
|
EDS attended.
|
|
45
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
10/12/2024
|
None of the observations have been attended.
|
|
46
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
10/12/2024
|
None of the observations have been attended.
|
|
47
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
12/12/2024
|
None of the observations have been attended.
|
|
48
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
16/12/2024
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
18/12/2024
|
Observations as raised by CF Bilaspur has been attended to vide this office letter No. 8494 dated 17.12.2024
|
|
50
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
20/12/2024
|
The point wise reply already stands sent to your office vide this e-office letter No. dated 05.12.2024 & the same has also been uploaded. This is for favour of information and necessary action at your end please.
|
|
51
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
26/12/2024
|
The list of 2183 road as submitted to Hon ble High court mentioning the S.N. of the instant proposal along with order of the court wherein court has directed for not taking the action taken against the offender and Forest Officials may be uploaded of part-I on Parivesh portal.
|
|
52
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
01/01/2025
|
The list of 2183 road as submitted to Hon ble High court mentioning the S.N. of the instant proposal along with order of the court wherein court has directed for not taking the action taken against the offender and Forest Officials may be uploaded of part-I on Parivesh portal.
|
|
53
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
02/01/2025
|
The list of 2183 road as submitted to Hon ble High court mentioning the S.N. of the instant proposal along with order of the court wherein court has directed for not taking the action taken against the offender and Forest Officials may be uploaded of part-I on Parivesh portal.
|
|
54
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
28/01/2025
|
The correction have been made as per the instruction received
|
|
55
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
25/02/2025
|
The reply submitted by you does not solve the purpose of EDS dated 01.01.2025. You are therefore requested to go through the EDS and submit detailed reply.
|
|
56
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
27/02/2025
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
10/03/2025
|
Observations as raised by CF Bilaspur has been attended to vide this office letter No. 12833 dated 07.03.2025
|
|
58
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
15/03/2025
|
EDS attended.
|
|
59
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
19/03/2025
|
The complete Status of the approved, under process and remaining proposal under violation as reported to Honable Hight court may be furnished.
|
|
60
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
19/03/2025
|
The complete Status of the approved, under process and remaining proposal under violation as reported to Honable Hight court may be furnished.
|
|
61
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
26/03/2025
|
The complete Status of the approved, under process and remaining proposal under violation as reported to Honable Hight court may be furnished.
|
|
62
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
03/04/2025
|
The correction have been made as per the instruction received
|
|
63
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
07/04/2025
|
Observations as raised by CF Bilaspur has been attended to vide this office letter No. 162 dated 05.04.2025
|
|
64
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
17/04/2025
|
EDS attended
|
|
65
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
23/04/2025
|
The complete Status of2183 roads i.e. approved, under process and remaining proposal under violation as reported to Honable High court are required.
|
|
66
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
26/04/2025
|
The complete Status of2183 roads i.e. approved, under process and remaining proposal under violation as reported to Honable High court are required.
|
|
67
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
28/04/2025
|
The complete Status of2183 roads i.e. approved, under process and remaining proposal under violation as reported to Honable High court are required.
|
|
68
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
10/06/2025
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
13/06/2025
|
Observations as raised by CF Bilaspur has been attended to vide this office letter No. 1948 dated 12.06.2025
|
|
70
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
19/06/2025
|
EDS attended.
|
|
71
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
21/06/2025
|
The complete Status of 2183 roads i.e. approved, under process and remaining proposal under violation as reported to Honable High court are required.
|
|
72
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
25/06/2025
|
The complete Status of 2183 roads i.e. approved, under process and remaining proposal under violation as reported to Honable High court are required.
|
|
73
|
DFO (Bilaspur)
|
EDS
|
User Agency (ee-bil2-hp@nic.in)
|
01/07/2025
|
The complete Status of 2183 roads i.e. approved, under process and remaining proposal under violation as reported to Hon'ble High court are required.
|
|
74
|
User Agency (ee-bil2-hp@nic.in)
|
REPLY
|
DFO (Bilaspur)
|
04/07/2025
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
05/07/2025
|
The correction have been made as per the instruction received
|
|
76
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
07/07/2025
|
Needful has been done
|
|
77
|
Nodal Officer
|
REPLY
|
State secretary
|
07/07/2025
|
Complete reply is submitted
|
|
78
|
State secretary
|
REPLY
|
Regional Office
|
07/07/2025
|
Complete reply is submitted
|
|