TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/17841/2016              (ii). Name of Project for which Forest Land is required : C/O kharsi Dughal road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Kharsi Dughal road is being constructed to provide the motor link to Village Dughal. The road will cater to the needs of population of about 325 souls and will give a boost to the local economy.              (iv). File no. : 8B/HP/06/18/2019/FC              (v). State : Himachal Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.21
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/17841/201602/03/201608/03/2016   17/02/2018   20/02/2018   16/03/2018 Nachan :16/03/2018Mandi:
  15/05/2018 (Nachan)

Himachal Pradesh:
04/07/2018
Himachal Pradesh:
29/01/2019
Shimla:
06/02/2019
31/07/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:05/03/2019  
Replied by State Government(Himachal Pradesh) on:22/06/2019  
Query raised by Regional Office (Shimla) on:26/07/2019  
Replied by State Government(Himachal Pradesh) on:12/03/2020  
Query raised by Regional Office (Shimla) on:30/04/2020  
Replied by State Government(Himachal Pradesh) on:20/07/2020  
Query raised by State Government (Himachal Pradesh) on:06/03/2019  
Replied by Nodal Officer (Himachal Pradesh) on:22/06/2019  
Query raised by State Government (Himachal Pradesh) on:27/07/2019  
Replied by Nodal Officer (Himachal Pradesh) on:12/03/2020  
Query raised by State Government (Himachal Pradesh) on:08/05/2020  
Replied by Nodal Officer (Himachal Pradesh) on:20/07/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:11/07/2018  
Replied by Circle(Mandi) on:29/11/2018  
Query raised by Nodal Officer (Himachal Pradesh) on:14/12/2018  
Replied by Circle(Mandi) on:15/01/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:06/03/2019  
Replied by Circle(Mandi) on:04/06/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:27/07/2019  
Replied by Circle(Mandi) on:10/02/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:20/02/2020  
Replied by Circle(Mandi) on:04/03/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:08/05/2020  
Replied by Circle(Mandi) on:13/07/2020  
Query raised by Circle (Mandi) on:18/05/2018  
Replied by DFO (Nachan) on:02/07/2018  
Query raised by Circle (Mandi) on:11/07/2018  
Replied by DFO (Nachan) on:28/11/2018  
Query raised by Circle (Mandi) on:14/12/2018  
Replied by DFO (Nachan) on:28/11/2018  
Query raised by Circle (Mandi) on:07/03/2019  
Replied by DFO (Nachan) on:10/01/2019  
Query raised by Circle (Mandi) on:28/05/2019  
Replied by DFO (Nachan) on:27/05/2019  
Query raised by Circle (Mandi) on:27/07/2019  
Replied by DFO (Nachan) on:03/06/2019  
Query raised by Circle (Mandi) on:22/02/2020  
Replied by DFO (Nachan) on:05/02/2020  
Query raised by Circle (Mandi) on:13/05/2020  
Replied by DFO (Nachan) on:03/03/2020  
Query raised by DFO (Nachan) on:17/03/2018  
Replied by UA on :31/03/2018  
Query raised by DFO (Nachan) on:11/05/2018  
Replied by UA on :11/05/2018  
Query raised by DFO (Nachan) on:22/05/2018  
Replied by UA on :02/06/2018  
Query raised by DFO (Nachan) on:04/06/2018  
Replied by UA on :08/06/2018  
Query raised by DFO (Nachan) on:29/06/2018  
Replied by UA on :02/07/2018  
Query raised by DFO (Nachan) on:21/07/2018  
Replied by UA on :28/08/2018  
Query raised by DFO (Nachan) on:12/09/2018  
Replied by UA on :24/09/2018  
Query raised by DFO (Nachan) on:24/09/2018  
Replied by UA on :29/09/2018  
Query raised by DFO (Nachan) on:01/10/2018  
Replied by UA on :06/10/2018  
Query raised by DFO (Nachan) on:26/10/2018  
Replied by UA on :20/11/2018  
Query raised by DFO (Nachan) on:14/12/2018  
Replied by UA on :09/01/2019  
Query raised by DFO (Nachan) on:14/03/2019  
Replied by UA on :27/03/2019  
Query raised by DFO (Nachan) on:02/04/2019  
Replied by UA on :05/04/2019  
Query raised by DFO (Nachan) on:29/07/2019  
Replied by UA on :20/08/2019  
Query raised by DFO (Nachan) on:28/08/2019  
Replied by UA on :03/09/2019  
Query raised by DFO (Nachan) on:07/09/2019  
Replied by UA on :29/01/2020  
Query raised by DFO (Nachan) on:31/01/2020  
Replied by UA on :05/02/2020  
Query raised by DFO (Nachan) on:15/05/2020  
Replied by UA on :02/07/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .