| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
26/08/2022
|
1. Check list No. 7 statement showing details of forest land proposed for diversion has not been found .
2. As per check list number 4 violation already constructed road in forest land has not been mentioned
3. As per inspection report of the committee the area in ha. for which forest land has already been broken / constructed has not been mentioned .
4. As per attached revenue papers of mauza Sanohat Khasra No. 422/390/380/104 the land is in the possession of Revenue department which needs to clarify whether this land is involved in FCA cases
|
|
|
2
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
27/02/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
10/03/2023
|
The CA site PF Kairy C1 5 ha. has been selected in lieu of diversion of forest land .please collect the KML file and GPS cordinates of CA site and provide the digital map of the same to this office and also attend the observations as raised on dated 26/8/2022 please
|
|
|
4
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
22/03/2023
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
25/03/2023
|
Please attend the observations as raised on dated 26-08-2022 and also provide the kml file of CA site and digital map thereof pl.
|
|
|
6
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
27/03/2023
|
The correction have been made as per the instruction received
|
|
|
7
|
CF (Nahan)
|
EDS
|
DFO (Rajgarh)
|
10/05/2023
|
EDS
|
|
|
8
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
11/05/2023
|
Please attend the observations of point number 1 to 5, 7 to 9 as raised by CCF Nahan as per enclosed letter please
|
|
|
9
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
29/06/2023
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Rajgarh)
|
REPLY
|
CF (Nahan)
|
15/07/2023
|
The case is here by recommended after attending the observations
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
07/08/2023
|
eds
|
|
|
12
|
CF (Nahan)
|
EDS
|
DFO (Rajgarh)
|
07/08/2023
|
EDS
|
|
|
13
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
09/08/2023
|
Please attend the observations raised by Nodal Officer from Point No. i to iii
|
|
|
14
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
05/09/2023
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Rajgarh)
|
REPLY
|
CF (Nahan)
|
19/09/2023
|
The case is hereby recommended after attending the observations
|
|
|
16
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
25/09/2023
|
Needful has been done.
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
05/10/2023
|
eds
|
|
|
18
|
CF (Nahan)
|
EDS
|
DFO (Rajgarh)
|
06/10/2023
|
EDS
|
|
|
19
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
09/10/2023
|
Kindly attend the observations number ii as pointed out by Nodal Officer-cum- FCA o/o Pr. CCF HoFF HP Shimla -I and upload the same on the portal
|
|
|
20
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
08/12/2023
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Rajgarh)
|
REPLY
|
CF (Nahan)
|
11/01/2024
|
The case is hereby recommended after attending the observations .
|
|
|
22
|
CF (Nahan)
|
EDS
|
DFO (Rajgarh)
|
12/01/2024
|
Please upload all the requisite document in additional information.
|
|
|
23
|
DFO (Rajgarh)
|
REPLY
|
CF (Nahan)
|
12/01/2024
|
The copy of documentary proof has been uploaded in the additional information .
|
|
|
24
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
12/01/2024
|
Needful has been done.
|
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
26/09/2024
|
The State Govt. may attend the shortcomings attached herewith.
|
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
28/09/2024
|
Please see the EDS raised by the MoEF&CC, Govt. of India
|
|
|
27
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
01/10/2024
|
EDS
|
|
|
28
|
CF (Nahan)
|
EDS
|
DFO (Rajgarh)
|
03/10/2024
|
EDS
|
|
|
29
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
08/10/2024
|
Please attend the observations EDS raised and upload the same on the portal.
|
|
|
30
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
19/12/2024
|
The correction have been made as per the instruction received
|
|
|
31
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
15/01/2025
|
The EDS as raised on dated 18-10-2024 has not been attended and the reply of observations has not been uploaded on the portal. hence the needful may be done and attend the observations raised previsouly pl
|
|
|
32
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
16/06/2025
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
02/07/2025
|
The EDS as raised on dated 18-10-2024 has not been attended and the reply of observations has not been uploaded on the portal. hence the needful may be done and attend the observations raised previously pl
|
|
|
34
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
30/07/2025
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
12/08/2025
|
The EDS as raised on dated 18-10-2024 has not been attended and the reply of observations has not been uploaded on the portal. hence you are therefore requested to do the needful may be done and attend the observations raised previously pl
|
|
|
36
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
18/08/2025
|
The correction have been made as per the instruction received
|
|
|
37
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
04/09/2025
|
The EDS as raised on dated 18-10-2024 has not been attended and the reply of observations has not been uploaded on the portal. hence you are therefore again requested to do the needful may be done and attend the observations raised previously pl
|
|
|
38
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
28/09/2025
|
The correction have been made as per the instruction received
|
|
|
39
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
24/10/2025
|
The EDS as raised on dated 18-10-2024 has not been attended as yet and the reply of observations has not been uploaded on the portal. hence you are therefore again requested to do the needful may be done and attend the observations raised previously pl.
|
|
|
40
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
26/11/2025
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
09/12/2025
|
The EDS as raised on dated 18-10-2024 has not been attended as yet and the reply of observations has not been uploaded on the portal. hence you are therefore again requested to do the needful may be done.
|
|
|
42
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
20/01/2026
|
The correction have been made as per the instruction received
|
|
|
43
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
23/01/2026
|
Please upload complete observations alongwith forwarding letter and hard copy thereof may be sent to this office please.
|
|
|
44
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
28/01/2026
|
The correction have been made as per the instruction received
|
|
|
45
|
DFO (Rajgarh)
|
EDS
|
User Agency (ee-raj-hp@nic.in)
|
03/02/2026
|
Pl upload the observations letter reply on the portal please.
|
|
|
46
|
User Agency (ee-raj-hp@nic.in)
|
REPLY
|
DFO (Rajgarh)
|
22/02/2026
|
The correction have been made as per the instruction received
|
|
|
47
|
DFO (Rajgarh)
|
REPLY
|
CF (Nahan)
|
03/03/2026
|
The observations as pointed out by the MOEF has been removed and uploaded on the portral
|
|
|
48
|
CF (Nahan)
|
EDS
|
DFO (Rajgarh)
|
05/03/2026
|
Please mention the serial No. of document as uploaded against the observation as raised by MoEF
|
|
|
49
|
DFO (Rajgarh)
|
REPLY
|
CF (Nahan)
|
06/03/2026
|
The needful has been done as per the instructions received
|
|
|
50
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
09/03/2026
|
Needful has been done.
|
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
16/03/2026
|
Complete reply is submitted
|
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
16/03/2026
|
Complete reply is submitted
|
|