TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/150852/2022              (ii). Name of Project for which Forest Land is required : C/O of link road from PHC Badahari Gurshali to Village Dawath Km 0/00 to 1/500.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : C/O link road from PHC Badahari Gurshali to Village Dawath Km 0/00 to 1/500 Road make a crucial contribution to economic development and growth and bring important social benefits. They are of vital importance in order to make a nation grow and develop. In addition, providing ac              (iv). File no. : FC/HPB/06/111/2022              (v). State : Himachal Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.4614
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/150852/202205/01/202207/01/2022   17/02/2022   19/02/2022   23/02/2022 Shimla(shimla) :23/02/2022Shimla:
  15/06/2022 (Shimla(shimla))

Himachal Pradesh:
17/06/2022
Himachal Pradesh:
17/08/2022
Shimla:
25/08/2022
18/09/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:06/09/2022  
Replied by State Government(Himachal Pradesh) on:26/05/2023  
Query raised by Regional Office (Shimla) on:14/11/2023  
Replied by State Government(Himachal Pradesh) on:20/07/2024  
Query raised by State Government (Himachal Pradesh) on:07/09/2022  
Replied by Nodal Officer (Himachal Pradesh) on:26/05/2023  
Query raised by State Government (Himachal Pradesh) on:16/11/2023  
Replied by Nodal Officer (Himachal Pradesh) on:20/07/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:30/06/2022  
Replied by Circle(Shimla) on:03/08/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:04/08/2022  
Replied by Circle(Shimla) on:05/08/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:07/09/2022  
Replied by Circle(Shimla) on:21/11/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:22/11/2022  
Replied by Circle(Shimla) on:25/02/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:23/03/2023  
Replied by Circle(Shimla) on:03/04/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:03/04/2023  
Replied by Circle(Shimla) on:19/05/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:16/11/2023  
Replied by Circle(Shimla) on:15/01/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:17/01/2024  
Replied by Circle(Shimla) on:15/07/2024  
Query raised by Circle (Shimla) on:04/07/2022  
Replied by DFO (Shimla(shimla)) on:01/08/2022  
Query raised by Circle (Shimla) on:04/08/2022  
Replied by DFO (Shimla(shimla)) on:05/08/2022  
Query raised by Circle (Shimla) on:07/09/2022  
Replied by DFO (Shimla(shimla)) on:21/11/2022  
Query raised by Circle (Shimla) on:22/11/2022  
Replied by DFO (Shimla(shimla)) on:25/02/2023  
Query raised by Circle (Shimla) on:23/03/2023  
Replied by DFO (Shimla(shimla)) on:03/04/2023  
Query raised by Circle (Shimla) on:03/04/2023  
Replied by DFO (Shimla(shimla)) on:16/05/2023  
Query raised by Circle (Shimla) on:16/11/2023  
Replied by DFO (Shimla(shimla)) on:12/01/2024  
Query raised by Circle (Shimla) on:18/01/2024  
Replied by DFO (Shimla(shimla)) on:04/07/2024  
Query raised by DFO (Shimla(shimla)) on:08/03/2022  
Replied by UA on :02/04/2022  
Query raised by DFO (Shimla(shimla)) on:26/04/2022  
Replied by UA on :04/05/2022  
Query raised by DFO (Shimla(shimla)) on:27/05/2022  
Replied by UA on :15/06/2022  
Query raised by DFO (Shimla(shimla)) on:04/07/2022  
Replied by UA on :30/07/2022  
Query raised by DFO (Shimla(shimla)) on:04/08/2022  
Replied by UA on :05/08/2022  
Query raised by DFO (Shimla(shimla)) on:10/09/2022  
Replied by UA on :26/09/2022  
Query raised by DFO (Shimla(shimla)) on:29/09/2022  
Replied by UA on :18/11/2022  
Query raised by DFO (Shimla(shimla)) on:22/11/2022  
Replied by UA on :02/12/2022  
Query raised by DFO (Shimla(shimla)) on:02/12/2022  
Replied by UA on :13/12/2022  
Query raised by DFO (Shimla(shimla)) on:14/12/2022  
Replied by UA on :20/02/2023  
Query raised by DFO (Shimla(shimla)) on:25/03/2023  
Replied by UA on :03/04/2023  
Query raised by DFO (Shimla(shimla)) on:13/04/2023  
Replied by UA on :09/05/2023  
Query raised by DFO (Shimla(shimla)) on:23/11/2023  
Replied by UA on :09/01/2024  
Query raised by DFO (Shimla(shimla)) on:18/01/2024  
Replied by UA on :31/03/2024  
Query raised by DFO (Shimla(shimla)) on:19/04/2024  
Replied by UA on :01/07/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .