Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
08/03/2016
|
Some shortcomings have been noticed in the proposal. Copy of EDS is attached.
|
|
2
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
11/03/2016
|
Pls attend to EDS.
|
|
3
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
20/04/2016
|
It has been submitted that the EDS attended and the required document uploaded
|
|
4
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
23/04/2016
|
Pls find EDS as attended to by DFO Mandi
|
|
5
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
26/04/2016
|
reply.
|
|
6
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
26/04/2016
|
Pls find the attended EDS
|
|
7
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
27/04/2016
|
Non of the observations has been attended. Attend all the observations & upload the requisite documents on the Web portal.
|
|
8
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
04/05/2016
|
Please find attended to EDS
|
|
9
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
16/05/2016
|
In reply to observation No.1, the toposheet indicating the proposed CA site duly signd by DFO is required to be uploaded against column No.13 iv of online part ii and not against EDS. Please uploaded the requisite toposheet agnaist column No.13 iv of online part- ii.
|
|
10
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
16/05/2016
|
In reply to observation No.1, the toposheet indicating the proposed CA site duly signd by DFO is required to be uploaded against column No.13 iv of online part ii and not against EDS. Please uploaded the requisite toposheet agnaist column No.13 iv of online part- ii.
|
|
11
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
20/07/2016
|
madam,
Duly signed Survey sheet has been uploaded.
DFO Mandi
|
|
12
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
20/07/2016
|
Needful done pls.
|
|