Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
16/10/2021
|
The proposal earliest sent to your office duly countersigned by undersigned has not been submitted with hard copies . The same may be sent to this office so that further action into the matter taken accordingly
|
|
2
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
07/04/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
06/03/2023
|
Update all pdf documents related part to with revenue papers
|
|
4
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
06/03/2023
|
The correction have been made as per the instruction received
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
24/06/2023
|
The shortcomings may be attended
|
|
6
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/06/2023
|
ACS Forests raised observations
|
|
7
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
24/06/2023
|
eds
|
|
8
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
27/06/2023
|
EDS attached your are requested to submit the reply as per point No. 4
|
|
9
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
12/07/2023
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
01/12/2023
|
certificate of non availability of non forest land for compensatory afforestation obtained from DC concerned has not found with proposal folder. You are requested to submit the same to this office so that further action could be taken accordingly.
|
|
11
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
03/10/2024
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
28/10/2024
|
The reply submitted by you is not satifactory. You are therefore requested to do the needfull.
|
|
13
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
13/11/2024
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
20/11/2024
|
The reply submitted by you is not satifactory. You are therefore requested to do the needfull.
|
|
15
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
28/12/2024
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
27/01/2025
|
You are requested that the submit the proper reply with in written and also uploaded in online portal
|
|
17
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
05/02/2025
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
13/02/2025
|
Your are once again requested submit the proper reply within written and also uplaoded in online portal and EDS.
|
|
19
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
12/03/2025
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
08/04/2025
|
EDS Attached
|
|
21
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
11/04/2025
|
You have uploaded the annexure along with the forwarding letter whereas it was ro be Upload in Part-I and Part-II. Please upload the same.
|
|
22
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
10/06/2025
|
Necessary corretion has been done
|
|
23
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
30/06/2025
|
Reply given as per attached
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
05/07/2025
|
Reply to ACS Forest Observations
|
|