| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
28/12/2021
|
Please attend as per attachment
|
|
|
2
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
17/08/2024
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
29/11/2024
|
Please mark all components on KML file of proposed file as per B-2 Component wise breakup
|
|
|
4
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
15/02/2025
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
20/02/2025
|
Please mark all components on KML file of proposed file as per B-2 Component wise breakup
|
|
|
6
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
02/04/2025
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
26/04/2025
|
in this regard User Agency is requested that kindly upload all checklist under FCA, 1980
|
|
|
8
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
26/05/2025
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
24/06/2025
|
Please mark all components on KML file of proposed file as per B-2 Component wise breakup
|
|
|
10
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
16/07/2025
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
22/08/2025
|
Please mark all components on KML file of proposed file as per B-2 Component wise breakup
|
|
|
12
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
28/09/2025
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
29/09/2025
|
From the perusal of the proposal, the proposal is required to be processed on PARIVESH 2.0 as per the FCA Rules, 2023. You are therefore requested to upload the proposal on PARIVESH 2.0.
|
|
|
14
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
08/11/2025
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml1-hp@nic.in)
|
05/12/2025
|
From the perusal of the proposal, the proposal is required to be processed on PARIVESH 2.0 as per the FCA Rules, 2023. You are therefore requested to upload the proposal on PARIVESH 2.0.
|
|
|
16
|
User Agency (ee-sml1-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
22/02/2026
|
The correction have been made as per the instruction received
|
|