| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
24/01/2019
|
Observation raised as per the letter attached be attended to and the complete case be resubmitted
|
|
|
2
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
01/07/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
10/07/2019
|
Please complete the proposal as per copy of EDS is attached.
|
|
|
4
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
11/07/2019
|
Please attend the attached EDS
|
|
|
5
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
11/07/2019
|
EDS
|
|
|
6
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
07/10/2019
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
07/10/2019
|
The EDS has been attended
|
|
|
8
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
09/10/2019
|
The EDS has been attended as per the attached reply
|
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
06/12/2019
|
state govt. may attend the following shortcomings as per the attachment here
|
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
06/12/2019
|
EDS
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
06/12/2019
|
EDS
|
|
|
12
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
09/12/2019
|
Please attend the EDS
|
|
|
13
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
10/12/2019
|
EDS
|
|
|
14
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
14/12/2019
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
24/01/2020
|
EDS has been attended
|
|
|
16
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
24/01/2020
|
EDS attended
|
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
04/02/2020
|
Complete reply is submitted.
|
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
04/02/2020
|
Complete reply is submitted.
|
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
19/02/2020
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
20/02/2020
|
EDS
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
20/02/2020
|
EDS
|
|
|
22
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
25/02/2020
|
Please attend the observation
|
|
|
23
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
04/04/2020
|
The permission install prefabricated structure on the sight was given by the then
Deputy Commissioner Lahaul & Spiti. Since user Agency has already submitted the consent to deposite the cost of Penal CA along with cost of NPV & CA, the violation may kindly be regularized by imposing Penal CA or any other penalty deemed fit.
|
|
|
24
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
07/04/2020
|
The hard copy of the reply to the EDS be submitted to this office.
|
|
|
25
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
28/05/2020
|
the permission install prefabricated structure on the site was given by then dupty commissioner Lahaul &Spiti, since user Agency has already submitted the consent to desposite the cost of Penal CA along with cost of NPV & CA, the violation may kindly be regularized by imposing Penal CA or any other penalty deemed fit.
|
|
|
26
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
28/05/2020
|
the permission install prefabricated structure on the site was given by then dupty commissioner Lahaul &Spiti, since user Agency has already submitted the consent to desposite the cost of Penal CA along with cost of NPV & CA, the violation may kindly be regularized by imposing Penal CA or any other penalty deemed fit.
|
|
|
27
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
28/05/2020
|
the permission install prefabricated structure on the site was given by then dupty commissioner Lahaul &Spiti, since user Agency has already submitted the consent to desposite the cost of Penal CA along with cost of NPV & CA, the violation may kindly be regularized by imposing Penal CA or any other penalty deemed fit.
|
|
|
28
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
18/06/2020
|
EDS attended
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
24/06/2020
|
EDS
|
|
|
30
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
24/06/2020
|
EDS
|
|
|
31
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
26/09/2020
|
Reply of EDS sent to cf...
With regards .
|
|
|
32
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
21/10/2020
|
EDS attended
|
|
|
33
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
03/11/2020
|
EDS
|
|
|
34
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
04/11/2020
|
EDS
|
|
|
35
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
28/01/2021
|
In this case as per observation raised, action has to be taken under section 1.21 of FCA act 1980.
The Show cause notice has been issued to the concerned staff and the replies are awaited.The case is under active consideration and there is no delay on the part of division.
The disciplinary action will be take time and the case is processed as the replies of the concerned staff are received in this office.
|
|
|
36
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
28/01/2021
|
Please submit the reply as per the EDS raised by Nodal Officer FCA
|
|
|
37
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
20/02/2021
|
The Comments of Deputy Commissioner district Lahaul Spiti has been sought. further action will be taken on receiving the comments from Deputy Commissioner Lahaul Spiti as well as User Agency . User Agency is required to HP DIET to supply the requisite information at the earliest.
|
|
|
38
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
23/02/2021
|
Please referred back the case online to this office only after submitting the reply in hard form.
|
|
|
39
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
25/02/2021
|
Please submit the comments related the case along with comments of Deputy Commissioner for further action.
|
|
|
40
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
17/06/2021
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
21/06/2021
|
please enclosed find herewith .
|
|
|
42
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
13/07/2021
|
The correction have been made as per the instruction received
|
|
|
43
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
19/07/2021
|
The correction has been done as per the instruction received.
|
|
|
44
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
02/08/2021
|
The reply to the observation raised by Nodal Officer is incomplete.
|
|
|
45
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
17/08/2021
|
kindly please find the attachment
|
|
|
46
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
17/06/2023
|
The correction have been made as per the instruction received
|
|
|
47
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
23/06/2023
|
You are requested to submit the reply in accordance out letter no 6012-16 dated 03/02/2021
|
|
|
48
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
07/12/2023
|
The correction have been made as per the instruction received
|
|
|
49
|
DFO (Lahaul)
|
EDS
|
User Agency (ashokgbpihed@rediffmail.com)
|
03/06/2024
|
EDS reply Letter not found attached
|
|
|
50
|
User Agency (ashokgbpihed@rediffmail.com)
|
REPLY
|
DFO (Lahaul)
|
29/09/2025
|
The correction have been made as per the instruction received
|
|