TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/Others/155916/2022              (ii). Name of Project for which Forest Land is required : Press Club Building at Changer Sector Bilaspur (HP)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest land is required for the Diversion of 0.02885 Hectare of forest land in favour of District Public relation Officer District Bilaspur HP for the construction of Press Club Building at Changer Sector Bilaspur, within the jurisdiction of Bilaspur Forest Division Distt. Bilaspur,HP.              (iv). File no. : FC/HPB/09/158/2022              (v). State : Himachal Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.02885
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/Others/155916/202227/05/202204/06/2022   18/06/2022   02/07/2022   08/07/2022 Bilaspur :08/07/2022Bilaspur:
  31/08/2022 (Bilaspur)

Himachal Pradesh:
02/09/2022
Himachal Pradesh:
17/09/2022
Shimla:
01/10/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:21/11/2022  
Replied by State Government(Himachal Pradesh) on:20/02/2023  
Query raised by Regional Office (Shimla) on:26/06/2023  
Replied by State Government(Himachal Pradesh) on:26/08/2023  
Query raised by Regional Office (Shimla) on:20/10/2023  
Replied by State Government(Himachal Pradesh) on:20/12/2023  
Query raised by Regional Office (Shimla) on:09/02/2024  
Replied by State Government(Himachal Pradesh) on:19/09/2024  
Query raised by Regional Office (Shimla) on:03/12/2024  
Replied by State Government(Himachal Pradesh) on:11/02/2025  
Query raised by Regional Office (Shimla) on:25/03/2025  
Replied by State Government(Himachal Pradesh) on:12/09/2025  
Query raised by State Government (Himachal Pradesh) on:23/11/2022  
Replied by Nodal Officer (Himachal Pradesh) on:20/02/2023  
Query raised by State Government (Himachal Pradesh) on:28/06/2023  
Replied by Nodal Officer (Himachal Pradesh) on:26/08/2023  
Query raised by State Government (Himachal Pradesh) on:21/10/2023  
Replied by Nodal Officer (Himachal Pradesh) on:20/12/2023  
Query raised by State Government (Himachal Pradesh) on:09/02/2024  
Replied by Nodal Officer (Himachal Pradesh) on:19/09/2024  
Query raised by State Government (Himachal Pradesh) on:04/12/2024  
Replied by Nodal Officer (Himachal Pradesh) on:11/02/2025  
Query raised by State Government (Himachal Pradesh) on:25/03/2025  
Replied by Nodal Officer (Himachal Pradesh) on:12/09/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:23/11/2022  
Replied by Circle(Bilaspur) on:13/02/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:28/06/2023  
Replied by Circle(Bilaspur) on:14/07/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:20/07/2023  
Replied by Circle(Bilaspur) on:04/08/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:08/08/2023  
Replied by Circle(Bilaspur) on:10/08/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:21/10/2023  
Replied by Circle(Bilaspur) on:29/11/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:30/11/2023  
Replied by Circle(Bilaspur) on:13/12/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:09/02/2024  
Replied by Circle(Bilaspur) on:22/03/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:27/03/2024  
Replied by Circle(Bilaspur) on:24/08/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:04/12/2024  
Replied by Circle(Bilaspur) on:18/12/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:20/12/2024  
Replied by Circle(Bilaspur) on:02/01/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:06/01/2025  
Replied by Circle(Bilaspur) on:30/01/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:25/03/2025  
Replied by Circle(Bilaspur) on:06/08/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:08/08/2025  
Replied by Circle(Bilaspur) on:28/08/2025  
Query raised by Circle (Bilaspur) on:24/11/2022  
Replied by DFO (Bilaspur) on:10/02/2023  
Query raised by Circle (Bilaspur) on:01/07/2023  
Replied by DFO (Bilaspur) on:11/07/2023  
Query raised by Circle (Bilaspur) on:21/07/2023  
Replied by DFO (Bilaspur) on:02/08/2023  
Query raised by Circle (Bilaspur) on:09/08/2023  
Replied by DFO (Bilaspur) on:10/08/2023  
Query raised by Circle (Bilaspur) on:25/10/2023  
Replied by DFO (Bilaspur) on:25/11/2023  
Query raised by Circle (Bilaspur) on:01/12/2023  
Replied by DFO (Bilaspur) on:12/12/2023  
Query raised by Circle (Bilaspur) on:12/02/2024  
Replied by DFO (Bilaspur) on:19/03/2024  
Query raised by Circle (Bilaspur) on:27/03/2024  
Replied by DFO (Bilaspur) on:23/08/2024  
Query raised by Circle (Bilaspur) on:04/12/2024  
Replied by DFO (Bilaspur) on:10/12/2024  
Query raised by Circle (Bilaspur) on:20/12/2024  
Replied by DFO (Bilaspur) on:02/01/2025  
Query raised by Circle (Bilaspur) on:06/01/2025  
Replied by DFO (Bilaspur) on:28/01/2025  
Query raised by Circle (Bilaspur) on:26/03/2025  
Replied by DFO (Bilaspur) on:22/07/2025  
Query raised by Circle (Bilaspur) on:29/07/2025  
Replied by DFO (Bilaspur) on:30/07/2025  
Query raised by Circle (Bilaspur) on:11/08/2025  
Replied by DFO (Bilaspur) on:14/08/2025  
Query raised by DFO (Bilaspur) on:20/07/2022  
Replied by UA on :29/07/2022  
Query raised by DFO (Bilaspur) on:13/12/2022  
Replied by UA on :09/01/2023  
Query raised by DFO (Bilaspur) on:30/10/2023  
Replied by UA on :18/11/2023  
Query raised by DFO (Bilaspur) on:04/12/2023  
Replied by UA on :07/12/2023  
Query raised by DFO (Bilaspur) on:16/02/2024  
Replied by UA on :13/03/2024  
Query raised by DFO (Bilaspur) on:28/03/2024  
Replied by UA on :17/08/2024  
NOTE:- Proposal is pending at Regional Office .
Close(X)
Close(X)
Please wait ...