Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
27/05/2019
|
Attend the observations as raised vide this office memo No. 850 dated 06-05-2019.
|
|
2
|
DFO (Paonta)
|
EDS
|
User Agency (randeepsinghsaini1122@gmail.com)
|
23/08/2019
|
please upload the revised maps of check list 5 and check list No.4, 10 and approach road map report etc.
|
|
3
|
User Agency (randeepsinghsaini1122@gmail.com)
|
REPLY
|
DFO (Paonta)
|
25/08/2019
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
26/08/2019
|
After attending all observation case is submitted for approval from the competent authority.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
02/09/2019
|
EDS
|
|
6
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
03/09/2019
|
EDS
|
|
7
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
07/09/2019
|
Observation has been obtained as awaited by higher ups. Now the case is submitted for further order please.
|
|
8
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
11/09/2019
|
Needful has been done.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
19/09/2019
|
please complete the proposal as per copy of EDS is attached
|
|
10
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
20/09/2019
|
please complete the proposal as per copy of EDS is attached
|
|
11
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
03/10/2019
|
All observation of this case has been attended as raised by higher ups. Now the case is submitted for further action in to the matter please.
|
|
12
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
05/10/2019
|
Needful has been done.
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
29/11/2019
|
EDS
|
|
14
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
29/11/2019
|
EDS
|
|
15
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
30/11/2019
|
EDS
|
|
16
|
DFO (Paonta)
|
EDS
|
User Agency (randeepsinghsaini1122@gmail.com)
|
05/12/2019
|
As observation raised by higher ups in this matter, you are requested take the matter with Industry department at your level also.
|
|
17
|
User Agency (randeepsinghsaini1122@gmail.com)
|
REPLY
|
DFO (Paonta)
|
08/12/2019
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
08/12/2019
|
As observation raised by higher authority has been obtained through user agency and hard copy of the same has already sent your office.
|
|
19
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
09/12/2019
|
Needful has been done.
|
|
20
|
Nodal Officer
|
REPLY
|
State secretary
|
02/01/2020
|
Complete reply is submitted.
|
|
21
|
Head Office
|
EDS
|
State secretary
|
14/05/2020
|
EDS
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
16/05/2020
|
EDS
|
|
23
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
16/05/2020
|
EDS
|
|
24
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
20/05/2020
|
EDS
|
|
25
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
24/06/2020
|
After attending the observation case is re-submitted for in-principle approval, hard copy of the same already stand submitted to your good office.
|
|
26
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
25/06/2020
|
Needful has been done.
|
|
27
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
17/07/2020
|
EDS
|
|
28
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
17/07/2020
|
EDS
|
|
29
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
27/07/2020
|
The matter will be decide at the level of higher authority for specific comments on adverse impact on Asan Barrage conservation Reserve.
|
|
30
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
28/07/2020
|
The matter will be decide at the level of higher authority for specific comments on adverse impact on Asan Barrage conservation Reserve.
|
|
31
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
14/08/2020
|
EDS
|
|
32
|
CF (Nahan)
|
EDS
|
DFO (Paonta)
|
14/08/2020
|
EDS
|
|
33
|
DFO (Paonta)
|
REPLY
|
CF (Nahan)
|
17/08/2020
|
after obtaining observation case is submitted for approval
|
|
34
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
17/08/2020
|
Needful has been done.
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
18/08/2020
|
Complete reply is submitted.
|
|
36
|
State secretary
|
REPLY
|
Head Office
|
19/08/2020
|
Complete reply is submitted.
|
|