Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
10/12/2019
|
May send the complete case in all respect .
|
|
2
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
02/01/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
07/01/2020
|
please attend the shortcomings as pointed out by this office.
|
|
4
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
03/03/2020
|
The correction have been made as per the instruction received
|
|
5
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
07/03/2020
|
The proposal not received physically
|
|
6
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
07/03/2020
|
please attend the shortcomings as pointed out by this office immediately.
|
|
7
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
12/03/2020
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
13/03/2020
|
The needful has been done as per instructions received.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
14/05/2020
|
Please complete the proposal as per copy of EDS is attached.
|
|
10
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
14/05/2020
|
Attend observations raised by Nodal Officer
|
|
11
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
14/05/2020
|
Attend observations raised by Nodal Officer
|
|
12
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
19/05/2020
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
22/05/2020
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
22/05/2020
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
22/05/2020
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
22/05/2020
|
The correction have been made as per the instruction received
|
|
17
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
01/06/2020
|
EDS attended.
|
|
18
|
Regional Office
|
EDS
|
State secretary
|
06/07/2020
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
07/07/2020
|
EDS
|
|
20
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
07/07/2020
|
EDS
|
|
21
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
08/07/2020
|
The observations be attended
|
|
22
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
14/07/2020
|
Attend observations raised by Nodal Officer
|
|
23
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
20/10/2021
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
25/10/2021
|
The correction have been made as per the instruction received
|
|
25
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
09/11/2021
|
EDS attended
|
|
26
|
Nodal Officer
|
REPLY
|
State secretary
|
17/11/2021
|
Complete reply is submitted.
|
|
27
|
State secretary
|
REPLY
|
Regional Office
|
17/11/2021
|
Complete reply is submitted.
|
|
28
|
Regional Office
|
EDS
|
State secretary
|
06/12/2021
|
The State Govt. may attend the shortcomings attached herewith
|
|
29
|
State secretary
|
EDS
|
Nodal Officer
|
06/12/2021
|
EDS
|
|
30
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
06/12/2021
|
EDS
|
|
31
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
08/12/2021
|
EDS
|
|
32
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
09/12/2021
|
EDS
|
|
33
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
11/12/2021
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
13/12/2021
|
Please attend the shortcomings as raised by GoI, MoEF & CC at the earliest .
|
|
35
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
13/12/2021
|
The correction have been made as per the instruction received
|
|
36
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
15/12/2021
|
The correction have been made as per the instruction received
|
|
37
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
21/12/2021
|
The reply of point No.5 is incomplete. Please submit complete reply
|
|
38
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
21/12/2021
|
The reply of point No.5 is incomplete. Please submit complete reply
|
|
39
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
21/12/2021
|
The correction have been made as per the instruction received
|
|
40
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
25/12/2021
|
The correction have been made as per the instruction received
|
|
41
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
01/01/2022
|
Hard copy of relpy not received in this office
|
|
42
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
04/01/2022
|
Stand Submitted vide this office letter No.FCA/6558 dated 3.1.2022
|
|
43
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
07/01/2022
|
EDS attended
|
|
44
|
Nodal Officer
|
REPLY
|
State secretary
|
28/01/2022
|
Complete reply
|
|
45
|
State secretary
|
REPLY
|
Regional Office
|
28/01/2022
|
Complete reply
|
|
46
|
Regional Office
|
EDS
|
State secretary
|
07/03/2022
|
State Government may attend the shortcomings attached herewith
|
|
47
|
State secretary
|
EDS
|
Nodal Officer
|
09/03/2022
|
EDS
|
|
48
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
09/03/2022
|
EDS
|
|
49
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
28/03/2022
|
EDS
|
|
50
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
28/03/2022
|
EDS
|
|
51
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
29/03/2022
|
The correction have been made as per the instruction received
|
|
52
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
06/04/2022
|
The correction have been made as per the instruction received
|
|
53
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
18/04/2022
|
EDS attended
|
|
54
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
26/04/2022
|
EDS
|
|
55
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
30/04/2022
|
EDS
|
|
56
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
07/05/2022
|
The correction has been mase as per instruction received.
|
|
57
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
13/05/2022
|
EDS attended
|
|
58
|
Nodal Officer
|
REPLY
|
State secretary
|
21/05/2022
|
Complete reply is submitted
|
|
59
|
State secretary
|
REPLY
|
Regional Office
|
21/05/2022
|
Complete reply is submitted
|
|
60
|
Regional Office
|
EDS
|
State secretary
|
29/06/2022
|
The State Govt. may attend the shortcomings attached herewith
|
|
61
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2022
|
EDS
|
|
62
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
29/06/2022
|
EDS
|
|
63
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
30/06/2022
|
EDS
|
|
64
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
30/06/2022
|
EDS
|
|
65
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
20/07/2022
|
The correction have been made as per the instruction received
|
|
66
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
06/09/2022
|
The correction have been made as per the instruction received
|
|
67
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
28/09/2022
|
Observations has been attended.
|
|
68
|
Nodal Officer
|
REPLY
|
State secretary
|
20/10/2022
|
Complete reply is submitted please and uploaded on the web portal.
|
|
69
|
State secretary
|
REPLY
|
Regional Office
|
20/10/2022
|
Complete reply is submitted please and uploaded on the web portal.
|
|
70
|
Regional Office
|
EDS
|
State secretary
|
01/12/2022
|
The State Government may attend the shortcomings attached herewith.
|
|
71
|
State secretary
|
EDS
|
Nodal Officer
|
03/12/2022
|
eds
|
|
72
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
03/12/2022
|
eds
|
|
73
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
05/12/2022
|
EDS
|
|
74
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
06/12/2022
|
EDS
|
|
75
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
31/12/2022
|
The correction have been made as per the instruction received
|
|
76
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
15/02/2023
|
The correction have been made as per the instruction received
|
|
77
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
24/02/2023
|
observations have been attdended.
|
|
78
|
Nodal Officer
|
REPLY
|
State secretary
|
14/03/2023
|
Complete reply is submitted
|
|
79
|
State secretary
|
REPLY
|
Regional Office
|
14/03/2023
|
Complete reply is submitted
|
|
80
|
Regional Office
|
EDS
|
State secretary
|
25/09/2023
|
State govt. may attend the following shortcomings as per the attachment here
|
|
81
|
State secretary
|
EDS
|
Nodal Officer
|
26/09/2023
|
EDS
|
|
82
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
26/09/2023
|
EDS
|
|
83
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
28/09/2023
|
EDS
|
|
84
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
28/09/2023
|
EDS
|
|
85
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
21/10/2023
|
The correction have been made as per the instruction received
|
|
86
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
03/11/2023
|
Power Generation capacity certificate not found uploaded
|
|
87
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
03/11/2023
|
The correction have been made as per the instruction received
|
|
88
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
03/11/2023
|
EDS attended please
|
|
89
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
04/11/2023
|
wrong attachment has been added.
|
|
90
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
04/11/2023
|
EDS reply attached please
|
|
91
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
20/11/2023
|
observations have been attended.
|
|
92
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
21/11/2023
|
The area may be revised in part-II as per revised proposed area. The unnecessary/ old documents as uploaded against additional information detail of part II may be removed.
|
|
93
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
21/11/2023
|
The area may be revised in part-II as per revised proposed area. The unnecessary/ old documents as uploaded against additional information detail of part II may be removed.
|
|
94
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
05/12/2023
|
EDS attended please
|
|
95
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
13/12/2023
|
observations have been attended.
|
|
96
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
20/12/2023
|
The DFO has claimed to do the site inspection on 10.1.19. However the report has been signed on 15.1.20 i.e. more than 1 year by both the DFO and the RO. why this inordinate delay? Is the DFO inspecting the site and submitting the report the same perso
|
|
97
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
28/12/2023
|
The DFO has claimed to do the site inspection on 10.1.19. However the report has been signed on 15.1.20 i.e. more than 1 year by both the DFO and the RO. why this inordinate delay? Is the DFO inspecting the site and submitting the report the same perso
|
|
98
|
DFO (Kullu)
|
EDS
|
User Agency (gangananna@gmail.com)
|
08/01/2024
|
The DFO has claimed to do the site inspection on 10.1.2019. However the report has been signed on 15.1.2020 i.e. more than 1 year by both the DFO and the RO. Why this inordinate delay. Is the DFO inspecting the site and submitting the report the same person.
|
|
99
|
User Agency (gangananna@gmail.com)
|
REPLY
|
DFO (Kullu)
|
15/02/2024
|
The correction have been made as per the instruction received
|
|
100
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
16/02/2024
|
EDS attended please
|
|
101
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
19/02/2024
|
EDS attended please.
|
|
102
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
19/03/2024
|
1. Why has the vegetation category not changed to dense category as observed by GoI. 2. Has the CA file been uploaded on e-green watch.
|
|
103
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
19/03/2024
|
1. Why has the vegetation category not changed to dense category as observed by GoI. 2. Has the CA file been uploaded on e-green watch.
|
|
104
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
02/04/2024
|
EDS attended please.
|
|
105
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
09/04/2024
|
observations have been attended.
|
|
106
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
26/04/2024
|
The CA area be uploaded on e-green watch portal before stage-I approval.
|
|
107
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
27/04/2024
|
The CA area be uploaded on e-green watch portal before stage-I approval.
|
|
108
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
02/05/2024
|
EDS attended please
|
|
109
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
13/05/2024
|
EDS attended please.
|
|
110
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
11/06/2024
|
The reply submitted vide letter dated was scrutinize and observe that the observations raised by this office remains unattended. Plz. look into it.
|
|
111
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
12/06/2024
|
The reply submitted vide letter dated was scrutinize and observe that the observations raised by this office remains unattended. Plz. look into it.
|
|
112
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
21/06/2024
|
EDS attended please
|
|
113
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
02/07/2024
|
observations have been attended.
|
|
114
|
Nodal Officer
|
REPLY
|
State secretary
|
24/07/2024
|
Complete reply is submitted
|
|
115
|
State secretary
|
REPLY
|
Regional Office
|
24/07/2024
|
Complete reply is submitted
|
|