Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
30/09/2019
|
Please attend the observations
|
|
2
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
01/10/2019
|
Sir,
Please attend the observations raised by C F Kullu and submit the reply through online as well as in hard copies at the earliest.
|
|
3
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
27/11/2019
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
06/12/2019
|
Sir,
EDS raised by your office has been attended by User Agency. Re-submitted please.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
31/12/2019
|
EDS
|
|
6
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
31/12/2019
|
Please attend the EDS
|
|
7
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
07/01/2020
|
Please attend the observations raised by Nodal Officer and resubmit to this office.
|
|
8
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
30/01/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
25/02/2020
|
Sir,
Please attach the copy of comments of PCCF Wildlife and remove the undertaking from additional documents.
|
|
10
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
25/02/2020
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
03/03/2020
|
Sir,
Observations raised by Nodal Officer, HP has been attended by User Agency and this office. Re-submitted please.
|
|
12
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
05/03/2020
|
EDS attended
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
07/03/2020
|
The comments of CWLW have been received in this office , the PDF of the said comments has been mailed to DFO Parbati for uploading the same in online part I & II. return the proposal after uploading the comments.
|
|
14
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
11/03/2020
|
Complete reply is submitted
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
22/06/2020
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
22/06/2020
|
EDS
|
|
17
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
22/06/2020
|
EDS
|
|
18
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
23/06/2020
|
EDS
|
|
19
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
24/06/2020
|
Sir,
Please attend the observation raised by NRO Dehrudhun and submit the reply through on line as well as in hard copies to this office at the earliest please.
|
|
20
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
17/09/2020
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
09/11/2020
|
Sir,
After doing needful, proposal for diversion of forest land for construction of Hurla Top SHEP is submitted to your good office for further necessary action please.
|
|
22
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
12/11/2020
|
All observations attended.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
01/01/2021
|
EDS
|
|
24
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
08/01/2021
|
EDS
|
|
25
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
28/01/2021
|
Sir,
Kindly attend the observation raised by the Nodal Officer-cum-APCCF, O/O Pr. CCF Shimla and submit the same to this office after doing needful.
|
|
26
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
03/02/2021
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
09/02/2021
|
Sir,
After doing needful case for diversion of Forest land for construction of Hurla Top SHEP (3.5MW) is submitted for further necessary action please.
|
|
28
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
22/02/2021
|
EDS attended
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
03/03/2021
|
Complete reply is submitted please.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
03/03/2021
|
Complete reply is submitted please.
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
18/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
19/03/2021
|
EDS
|
|
33
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
19/03/2021
|
EDS
|
|
34
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
24/03/2021
|
EDS
|
|
35
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
31/03/2021
|
Sir,'
After doing needful case for diversion of forest land is resubmitted to your good office for further necessary action please.
|
|
36
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
07/04/2021
|
EDS attended
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
05/05/2021
|
Complete reply is submitted.
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
01/06/2021
|
Complete reply is submitted.
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
22/06/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
23/06/2021
|
EDS
|
|
41
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
23/06/2021
|
EDS
|
|
42
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
28/06/2021
|
EDS
|
|
43
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
20/07/2021
|
Kindly attend the observation as raised by GoI.
|
|
44
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
13/08/2021
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
24/08/2021
|
Sir,
After attended the observation raised by GoI, case is sent to your good office for further necessary action.
|
|
46
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
15/09/2021
|
EDS attended
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
28/09/2021
|
Complete reply is submitted.
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
28/09/2021
|
Complete reply is submitted.
|
|
49
|
RO/HQ
|
EDS
|
( ROSHIM )
|
08/06/2022
|
EDs raised to IRO Shimla
|
|
50
|
Regional Office
|
EDS
|
State secretary
|
22/07/2022
|
The State Govt. may attend the shortcomings attached herewith
|
|
51
|
State secretary
|
EDS
|
Nodal Officer
|
22/07/2022
|
eds
|
|
52
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
22/07/2022
|
eds
|
|
53
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
22/07/2022
|
EDS
|
|
54
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
22/07/2022
|
Sir,
After doing need for case is forwarded to your good office for further necessary action.
|
|
55
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
22/11/2022
|
please submit the reply of EDS raised by Integrated Regional office on 21.07.2022
|
|
56
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
16/02/2023
|
Sir,
Kindly attend the observation raised by Nodal Officer FCA and intimate this office accordingly.
|
|
57
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
16/05/2023
|
The correction have been made as per the instruction received
|
|
58
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
20/06/2023
|
Respected Maam,
After attending the observation raised by IRO case for diversion of Forest Land is resubmitted for further necessary action.
|
|
59
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
21/06/2023
|
Document regarding aerial distance from GHNP Annexure-iv has not been found uploaded.
|
|
60
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
27/06/2023
|
Respected Maam,
Needful has been done and resubmitted for further necessary action please.
|
|
61
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
30/06/2023
|
Point no. 5 and 6 has not been attended. Soil moisture conservation plan and wild life management plan required to be uploaded online.
|
|
62
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
03/07/2023
|
Sir,
Kindly attend the observation raised by CF Kullu accordingly and submit the same to this office.
|
|
63
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
05/07/2023
|
The correction have been made as per the instruction received
|
|
64
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
05/07/2023
|
respected madam,
Case is resubmitted for further necessary action telephonic direction received.
|
|
65
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
20/07/2023
|
observations have been attended.
|
|
66
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
01/08/2023
|
EDS
|
|
67
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
01/08/2023
|
Eds
|
|
68
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
02/08/2023
|
Sir,
Kindly attend the EDS raised by Nodal Officer mentioned at point No. 4.
|
|
69
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
30/04/2024
|
The correction have been made as per the instruction received
|
|
70
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
20/07/2024
|
necessary observations has been attended by the UA , case is submitted for further necessary action please.
|
|
71
|
CF (Kullu)
|
EDS
|
DFO (Parbati)
|
22/07/2024
|
Reply letter duly signed by DFO has not been attached.
|
|
72
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
26/10/2024
|
Sir,
Kindly attend the observation raised by Nodal Officer FCA Shimla and submit the same to this office.
|
|
73
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
09/12/2024
|
The correction have been made as per the instruction received
|
|
74
|
DFO (Parbati)
|
EDS
|
User Agency (hurlatop@gmail.com)
|
17/12/2024
|
kindly attend these observations as raised by Nodal officer and send complete point wise reply along with the detail of documents uploaded against the column/Sr.
No immediately.
|
|
75
|
User Agency (hurlatop@gmail.com)
|
REPLY
|
DFO (Parbati)
|
04/04/2025
|
The correction have been made as per the instruction received
|
|
76
|
DFO (Parbati)
|
REPLY
|
CF (Kullu)
|
17/06/2025
|
Sir,
After attending observation raised by Nodal Officer FCA Shimla, case is resubmitted for further necessary action
|
|
77
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
26/06/2025
|
EDS attended please.
|
|