Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
04/01/2018
|
folder not received till date and same cannot be processed. .... sent back for re-submission alongwith folders.
|
|
2
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
24/01/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
10/05/2018
|
Several discrepancies has been noticed in Proposal folders submitted in shape of hard copy hence proposal folders are returned herewith with the remarks that complete the codal formalities and re-submit the case as discussed with you in the office of DFO Churah please.
|
|
4
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
14/05/2018
|
The correction have been made as per the instruction received
|
|
5
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
04/07/2018
|
please attend the observations as raised vide this office letter No. D-V-508/G/2320 dated 22.06.2018 and re-submite the case to this office complete in all respect.
|
|
6
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
25/07/2018
|
Needful has been done please.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
13/09/2018
|
Please complete the proposal as per copy of EDS is attached
|
|
8
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
13/09/2018
|
Please complete the proposal as per copy of EDS is attached
|
|
9
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
06/10/2018
|
Please attend the observations as asked by the higher ups and re-submit the case for further necessary action please.
|
|
10
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
13/11/2018
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
13/11/2018
|
submit the hard copy also
|
|
12
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
13/11/2018
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
04/02/2019
|
Submit a csae in shape of hard copy please.
|
|
14
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
31/05/2019
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
13/06/2019
|
Observation has been attended vide this office emo. No. 944 dated 13-06-2019 hence re-submitted for further action please.
|
|
16
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
20/06/2019
|
KML file of the project components is not found attached herewith. Please upload the same and submit case to this office.
|
|
17
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
03/07/2019
|
KML file of the project components is not found attached herewith. Please upload the same and submit case to this office.
|
|
18
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
08/07/2019
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
09/07/2019
|
It has been submitted by the user agency that KML file of project component has been uploaded hence re-submitted for further necessary action please.
|
|
20
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
09/07/2019
|
Numbers of trees as the online and hard copies are not matching. 2. The location details and area of 12 numbers CA patches is not given as uploaded in the online. Further it is also submitted that please go through strictly as per as per the MOEF GOI Notification dated 17.04.2019 in this regards, and comply to this point as raised by the Nodal Officer.
|
|
21
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
11/07/2019
|
Numbers of trees as the online and hard copies are not matching. 2. The location details and area of 12 numbers CA patches is not given as uploaded in the online. Further it is also submitted that please go through strictly as per as per the MOEF GOI Notification dated 17.04.2019 in this regards, and comply to this point as raised by the Nodal Officer.
|
|
22
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
02/08/2019
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
03/08/2019
|
Neddful has ben done and submitted vide this offie memo. No. 2329 dated 3/8/2019 please.
|
|
24
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
07/08/2019
|
Still number of trees are not matching online entered and in hard copy. Please correct it.
|
|
25
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
07/08/2019
|
Correction has been done.
|
|
26
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
09/08/2019
|
Reply of EDS is not found uploaded. Please attached it.
|
|
27
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
09/08/2019
|
Hard copy has already been submitted in your office by hand.
|
|
28
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
13/08/2019
|
attend
|
|
29
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
13/08/2019
|
Attended.
|
|
30
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
20/08/2019
|
The observations as raised by you have been attended by the User Agency and DFO. Submitted for further necessary action at your end please.
|
|
31
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
31/08/2019
|
The reply to point No.10 is not in order. Although the certificate from WL point of view has been uploaded but the distance of the proposed project from the protected area /Eco sensitive zone of protected areas has not been mentioned in the uploaded certificate.
|
|
32
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
02/09/2019
|
The Distance of the proposed site from the nearst Wild Life Sanctuary is 15.60 Km. The necessary certificate in this regard issued by the PCCF (WL) Shimla is already placed in the proposal folder at Page No. 128A. Same is also attached in the EDS.
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
31/10/2019
|
state govt. may attend the following shortcomings as per the attachment here
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
01/11/2019
|
EDS
|
|
35
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
01/11/2019
|
EDS
|
|
36
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
02/11/2019
|
Please attend the observation as raised by the Regional Office.
|
|
37
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
04/11/2019
|
Please attend the observation as raised by the Regional Office.
|
|
38
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
05/12/2019
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
11/12/2019
|
EDS attended hence re-submitted for favour further n/action please.
|
|
40
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
18/12/2019
|
EDS has been attended by the User Agency and DFO Churah. Reply to the EDS is added please.
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
28/12/2019
|
Complete reply is submitted.
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
28/12/2019
|
Complete reply is submitted.
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
04/02/2020
|
The proposal was discussed in the REC meeting held on 29.01.2020. State Government may attend the shortcomings as per the minutes of REC meeting attached herewith.
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
04/02/2020
|
EDS
|
|
45
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
04/02/2020
|
EDS
|
|
46
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
04/02/2020
|
Attend the points raised by the REC and submit the point wise reply to this office at the earliest.
|
|
47
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
07/02/2020
|
Attend the points raised by the REC and submit the point wise reply to this office at the earliest.
|
|
48
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
30/06/2020
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
02/07/2020
|
Observations have been attended hence re-submitted for further necessary action please.
|
|
50
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
04/07/2020
|
Reply and documents have been submitted by UA and DFO to the points raised by the REC. Point wise reply is attache herewith.
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
18/07/2020
|
COMPLETE REPLY IS SUBMITTED.
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
18/07/2020
|
Complete reply is submitted
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
31/07/2020
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
03/08/2020
|
may attend to the shortcomings mentioned in the attached document
|
|
55
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
03/08/2020
|
may attend to the shortcomings mentioned in the attached document
|
|
56
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
05/08/2020
|
Please attend the observations as raised by RO.
|
|
57
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
06/08/2020
|
Please attend the observations as raised by RO.
|
|
58
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
06/08/2020
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
14/08/2020
|
Observation has been attended hence re-submitted for further necessary action please.
|
|
60
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
18/08/2020
|
Reply to observation is attached please.
|
|
61
|
Nodal Officer
|
REPLY
|
State secretary
|
15/09/2020
|
Complete reply is submitted.
|
|
62
|
State secretary
|
REPLY
|
Regional Office
|
15/09/2020
|
Complete reply is submitted.
|
|
63
|
Regional Office
|
EDS
|
State secretary
|
08/10/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
64
|
State secretary
|
EDS
|
Nodal Officer
|
09/10/2020
|
EDS
|
|
65
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
09/10/2020
|
EDS
|
|
66
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
09/10/2020
|
Please attend the EDS as raised by RO.
|
|
67
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
13/10/2020
|
The reply has already sent through email to nodal office on dated 1/10/2020 and also enclosed here for further necessary action.
|
|
68
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
13/10/2020
|
The reply has already sent by DFO through email to nodal office on dated 1/10/2020 and also enclosed here for further necessary action. - As submitted by DFO is forwarded for information and necessary action please.
|
|
69
|
Nodal Officer
|
REPLY
|
State secretary
|
16/10/2020
|
The reply has already been sent to your office.
|
|
70
|
State secretary
|
REPLY
|
Regional Office
|
16/10/2020
|
The reply has already been sent to your office.
|
|
71
|
RO/HQ
|
EDS
|
( ROSHIM )
|
31/12/2020
|
EDS sought on 29.12.2020 from SFD.
|
|
72
|
Regional Office
|
EDS
|
State secretary
|
31/12/2020
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
73
|
State secretary
|
EDS
|
Nodal Officer
|
04/01/2021
|
EDS
|
|
74
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
04/01/2021
|
EDS
|
|
75
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
05/01/2021
|
Please attend the EDS.
|
|
76
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
20/01/2021
|
Please attend the EDS.
|
|
77
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
29/01/2021
|
The correction have been made as per the instruction received
|
|
78
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
29/01/2021
|
Obeservation has been attended hence re-submitted for further necessary action please.
|
|
79
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
03/02/2021
|
EDS has been attended, Reply attached.
|
|
80
|
Nodal Officer
|
REPLY
|
State secretary
|
17/02/2021
|
Complete reply is submitted.
|
|
81
|
State secretary
|
REPLY
|
Regional Office
|
17/02/2021
|
Complete reply is submitted.
|
|
82
|
Regional Office
|
EDS
|
State secretary
|
23/07/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
83
|
State secretary
|
EDS
|
Nodal Officer
|
24/07/2021
|
EDS
|
|
84
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
24/07/2021
|
EDS
|
|
85
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
26/07/2021
|
EDS
|
|
86
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
27/07/2021
|
EDS
|
|
87
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
04/08/2021
|
The correction have been made as per the instruction received
|
|
88
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
04/08/2021
|
Needful has been done.
|
|
89
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
09/08/2021
|
EDS has been attended. Reply is attached.
|
|
90
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
21/09/2021
|
This office has requested to CEO-Cum-CCF (CAMPA) to supply the reply of the point No. 1 with regard to status of CAT Plan of Ravi Basin. Further, it has been collected from the office of CEO-Cum-CCF (CAMPA) that the information is being collected from the O/o CCF Chamba, which is still awaited. Hence, the proposal may be send online to CCF Chamba for doing the needful ple
|
|
91
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
22/09/2021
|
requisite information has been sent please.
|
|
92
|
Nodal Officer
|
REPLY
|
State secretary
|
11/10/2021
|
Complete reply is submitted.
|
|
93
|
State secretary
|
REPLY
|
Regional Office
|
11/10/2021
|
Complete reply is submitted.
|
|
94
|
Regional Office
|
EDS
|
State secretary
|
08/11/2021
|
The State Govt. may attend the shortcomings as per the minutes of REC attached herewith
|
|
95
|
State secretary
|
EDS
|
Nodal Officer
|
09/11/2021
|
REC MINUTES
|
|
96
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
09/11/2021
|
REC MINUTES
|
|
97
|
CF (Chamba)
|
EDS
|
DFO (Churah)
|
10/11/2021
|
REC Minutes of Meeting. Please do the needful.
|
|
98
|
DFO (Churah)
|
EDS
|
User Agency (sepcmandi@hpseb.in)
|
12/11/2021
|
REC Minutes of Meeting please do the needful
|
|
99
|
User Agency (sepcmandi@hpseb.in)
|
REPLY
|
DFO (Churah)
|
01/12/2021
|
The correction have been made as per the instruction received
|
|
100
|
DFO (Churah)
|
REPLY
|
CF (Chamba)
|
02/12/2021
|
The correction have been made as per the instruction received
|
|
101
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
04/12/2021
|
EDS is attended.
|
|
102
|
Nodal Officer
|
REPLY
|
State secretary
|
09/12/2021
|
Complete reply is submitted
|
|
103
|
State secretary
|
REPLY
|
Regional Office
|
09/12/2021
|
Complete reply is submitted
|
|