Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
11/03/2022
|
please send the 4 Nos of proposal folders complete in all respect to this office at the earliest.
|
|
2
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
22/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
24/03/2022
|
Please send the four Nos of proposal folders complete in all respect at the earliest please.
|
|
4
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
21/05/2022
|
The correction have been made as per the instruction received
|
|
5
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
14/07/2022
|
The detail of already existing and proposed HEPs on the same nala/stream be provided
|
|
6
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
18/07/2022
|
The detail of already existing and proposed HEPs on the same nala/stream be provided
|
|
7
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
01/08/2022
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
20/08/2022
|
The correction have been made as per the instruction received
|
|
9
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
08/09/2022
|
correct the number of trees in online Part-II
|
|
10
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
08/09/2022
|
The number of trees be corrected as per observations raised by the Nodal officer
|
|
11
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
08/09/2022
|
correction has been made in online part-II with regard to trees
|
|
12
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
08/09/2022
|
DFO Kullu has corrected the number of trees in online Part-II.
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
21/04/2023
|
The State Government may attend the shortcomings attached herewith.
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
24/04/2023
|
eds
|
|
15
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
24/04/2023
|
eds
|
|
16
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
25/04/2023
|
EDS
|
|
17
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
26/04/2023
|
Please attend the observations
|
|
18
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
09/05/2023
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
07/06/2023
|
EDS attended please
|
|
20
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
13/06/2023
|
observations have been attended.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
19/06/2023
|
EDS
|
|
22
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
19/06/2023
|
EDS
|
|
23
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
20/06/2023
|
EDS
|
|
24
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
29/06/2023
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
30/06/2023
|
Please submit the complete reply to the observations
|
|
26
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
03/07/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
15/07/2023
|
EDS attended please
|
|
28
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
27/07/2023
|
observations have been attended.
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
07/08/2023
|
Reply to GoI Observations is attached herewith.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
07/08/2023
|
Please find attached herewith reply to the observations as raised by the Govt. of India 21.04.2023
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
29/11/2023
|
REPLY NOT ACCEPTED
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
29/11/2023
|
EDS
|
|
33
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
29/11/2023
|
EDS
|
|
34
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
29/11/2023
|
EDs
|
|
35
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
02/12/2023
|
EDS
|
|
36
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
08/01/2024
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
10/01/2024
|
observations have been attended.
|
|
38
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
11/01/2024
|
observations have been attended.
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
24/01/2024
|
Complete reply is submitted
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
24/01/2024
|
Complete reply is submitted
|
|
41
|
Regional Office
|
EDS
|
State secretary
|
12/03/2024
|
REPLY NOT ACCEPTED
|
|
42
|
State secretary
|
EDS
|
Nodal Officer
|
14/03/2024
|
EDS
|
|
43
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
14/03/2024
|
EDS
|
|
44
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
14/03/2024
|
Eds
|
|
45
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
14/03/2024
|
EDS
|
|
46
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
19/03/2024
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
21/03/2024
|
EDS attended please
|
|
48
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
23/03/2024
|
observation have been attended
|
|
49
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
06/04/2024
|
confirm whether this project is within the carrying capacity of the river Beas.
|
|
50
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
09/04/2024
|
confirm whether this project is within the carrying capacity of the river Beas.
|
|
51
|
DFO (Kullu)
|
EDS
|
User Agency (1973anujmahant@gmail.com)
|
09/04/2024
|
confirm whether this project is within the carrying capacity of the river Beas.
|
|
52
|
User Agency (1973anujmahant@gmail.com)
|
REPLY
|
DFO (Kullu)
|
09/04/2024
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
22/04/2024
|
EDS attended please
|
|
54
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
25/04/2024
|
observations has been attended.
|
|
55
|
Nodal Officer
|
REPLY
|
State secretary
|
04/05/2024
|
Complete reply is submitted
|
|
56
|
State secretary
|
REPLY
|
Regional Office
|
04/05/2024
|
Complete reply is submitted
|
|