Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
18/09/2016
|
The area being proposed for diversion is 12.4332 hac.,but area proosed for CA is 22.6876only whereas ist has to be double of the area proposed . Please see to it.
FRA certificate is nit attached.
|
|
2
|
DFO (J/Nagar)
|
EDS
|
User Agency (uhl14mwpoml@outlook.com)
|
21/09/2016
|
Attend the observation
|
|
3
|
User Agency (uhl14mwpoml@outlook.com)
|
REPLY
|
DFO (J/Nagar)
|
21/10/2016
|
The correction have been made as per the instruction received
|
|
4
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
24/10/2016
|
Area falling under component tunnel is exempted for CA vide MOEF letter no. 11-674/2014-FC dated 26.11.2015.So total land for compensatory afforeastaion is (12.4332-1.0894) 11.3438 x2=22.6876ha.user agency has also submitted FRA certificate
|
|
5
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
15/11/2016
|
Against column No.4 ii of online part-II,only 567 trees have been shown whereas as per enumerations lists & general abstract placed at P.No. 60-82 in the proposal folder 568 trees are involved in the present proposal. Necessary corrections is required to be made against column 4
|
|
6
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
16/11/2016
|
Against column No.4 ii of online part-II,only 567 trees have been shown whereas as per enumerations lists & general abstract placed at P.No. 60-82 in the proposal folder 568 trees are involved in the present proposal. Necessary corrections is required to be made against column 4
|
|
7
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
01/12/2016
|
EDS has been attended
|
|
8
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
02/12/2016
|
EDS has been attended to by DFO
|
|
9
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
07/12/2016
|
Still against column No.4 ii of online part-II,only 567 trees have been shown whereas as per enumerations lists & general abstract placed at P.No. 60-82 in the proposal folder 568 trees are involved in the present proposal. Necessary corrections is required to be made against column 4.
|
|
10
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
17/12/2016
|
Still against column No.4 ii of online part-II,only 567 trees have been shown whereas as per enumerations lists & general abstract placed at P.No. 60-82 in the proposal folder 568 trees are involved in the present proposal. Necessary corrections is required to be made against column 4.
|
|
11
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
19/12/2016
|
Needful has been done
|
|
12
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
20/12/2016
|
needful has been done by DFO
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
27/02/2017
|
The observations as raised in REC may be got attended online at the earliest please.
|
|
14
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
27/02/2017
|
The observations as raised by in REC meeting may be got attend online at the earliest please
|
|
15
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
27/02/2017
|
EDS Uploaded pertains to some other project. pl upload correct EDS.
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
27/02/2017
|
Reply.
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
28/04/2017
|
State Govt may attend to the shortcomings mentioned in the attached document.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2017
|
EDS
|
|
19
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
01/05/2017
|
EDS
|
|
20
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
01/05/2017
|
pls attend to EDS.
|
|
21
|
DFO (J/Nagar)
|
EDS
|
User Agency (uhl14mwpoml@outlook.com)
|
09/05/2017
|
pls attend to EDS.
|
|
22
|
User Agency (uhl14mwpoml@outlook.com)
|
REPLY
|
DFO (J/Nagar)
|
26/05/2017
|
The correction have been made as per the instruction received
|
|
23
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
07/06/2017
|
EDS attended
|
|
24
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
08/06/2017
|
EDS attended pls.
|
|
25
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
08/06/2017
|
All the components have not been shown in the single KML file. Please upload all component is single KmL file.
|
|
26
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
08/06/2017
|
All the components have not been shown in the single KML file. Please upload all component is single KmL file.
|
|
27
|
DFO (J/Nagar)
|
EDS
|
User Agency (uhl14mwpoml@outlook.com)
|
13/06/2017
|
All the components have not been shown in the single KML file. Please upload all component is single KmL file.pl attend EDS
|
|
28
|
User Agency (uhl14mwpoml@outlook.com)
|
REPLY
|
DFO (J/Nagar)
|
15/06/2017
|
The correction have been made as per the instruction received
|
|
29
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
16/06/2017
|
EDS attended
|
|
30
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
17/06/2017
|
EDS attended please.
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
19/06/2017
|
Complete reply is submitted.
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
19/06/2017
|
Complete reply is submitted.
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
29/06/2017
|
The proposal was discussed in the REC meeting held on 28/06/2017. The correction may be made as per REC decisions. The minutes of the meeting will soon be uploaded online.
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
30/06/2017
|
The proposal was discussed in the REC meeting held on 28/06/2017. The correction may be made as per REC decisions. The minutes of the meeting will soon be uploaded online.
|
|
35
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
30/06/2017
|
The proposal was discussed in the REC meeting held on 28/06/2017. The correction may be made as per REC decisions. The minutes of the meeting will soon be uploaded online.
|
|
36
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
04/07/2017
|
The proposal was discussed in the REC meeting held on 28/06/2017. The correction may be made as per REC decisions. The minutes of the meeting will soon be uploaded online.
|
|
37
|
DFO (J/Nagar)
|
EDS
|
User Agency (uhl14mwpoml@outlook.com)
|
11/08/2017
|
Please attend the EDS
|
|
38
|
User Agency (uhl14mwpoml@outlook.com)
|
REPLY
|
DFO (J/Nagar)
|
17/09/2017
|
The correction have been made as per the instruction received
|
|
39
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
22/09/2017
|
EDS attended
|
|
40
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
25/09/2017
|
EDS been attended to.
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
09/10/2017
|
REPLY TO GOI OBSERVATIONS.
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
10/10/2017
|
Complete reply is submitted.
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
06/11/2017
|
The proposal was discussed in the REC meeting held on 30.10.2017. State Govt. may attend the shortcomings as per the minutes of REC meeting attached.
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
14/11/2017
|
Please complete the proposal as per copy of EDS is attached.
|
|
45
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
15/11/2017
|
Please get complete the proposal from User agency as per observations raised by REC during its meeting 30.10.2017,on Proposal No.FP/HP/HYD/13963/2015 for the diversion of 12.4332 ha of forest land in favour of M/S PURI OIL MILLS Ltd. for the construction of 14 MW UHL HEP.Copy of minutes of meeting is attached.
|
|
46
|
CF (Mandi)
|
EDS
|
DFO (J/Nagar)
|
18/11/2017
|
Please get complete the proposal from User agency as per observations raised by REC during its meeting 30.10.2017,on Proposal No.FP/HP/HYD/13963/2015 for the diversion of 12.4332 ha of forest land in favour of M/S PURI OIL MILLS Ltd. for the construction of 14 MW UHL HEP.Copy of minutes of meeting is attached.
|
|
47
|
DFO (J/Nagar)
|
EDS
|
User Agency (uhl14mwpoml@outlook.com)
|
26/12/2017
|
Please attend the observation raised by REC during its meeting 30.10.2017
|
|
48
|
User Agency (uhl14mwpoml@outlook.com)
|
REPLY
|
DFO (J/Nagar)
|
04/10/2018
|
The correction have been made as per the instruction received
|
|
49
|
DFO (J/Nagar)
|
REPLY
|
CF (Mandi)
|
15/10/2018
|
observations attended
|
|
50
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
15/10/2018
|
EDS attended to by user and field agency.
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
16/10/2018
|
Sir,
The reply to the observations pointed out in REC meeting dated 30.10.2017 is submitted please.
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
16/10/2018
|
Sir,
The reply to the observations pointed out in REC meeting dated 30.10.2017 is submitted please.
|
|