Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bilaspur)
|
EDS
|
User Agency (aiimsvinay2010@gmail.com)
|
08/10/2018
|
The proposal folder are still awaited.
|
|
2
|
User Agency (aiimsvinay2010@gmail.com)
|
REPLY
|
DFO (Bilaspur)
|
17/10/2018
|
The correction have been made as per the instruction received
|
|
3
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
29/10/2018
|
Hard copy of proposal not received. Pl send the same
|
|
4
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
31/10/2018
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
02/11/2018
|
The CA patches on toposheet uploaded against column No.13 iv are not tallying with the KML files.Further in site inspection report of DFO specific recommendations have not been made. Please upload revised corrected documents against appropriate columns.
|
|
6
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
02/11/2018
|
The CA patches on toposheet uploaded against column No.13 iv are not tallying with the KML files.Further in site inspection report of DFO specific recommendations have not been made. Please upload revised corrected documents against appropriate columns.
|
|
7
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
02/11/2018
|
The correction has been done made as per the instruction received
|
|
8
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
02/11/2018
|
corrections have been made.
|
|
9
|
Head Office
|
EDS
|
State secretary
|
03/01/2019
|
EDS
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
04/01/2019
|
EDS
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bilaspur)
|
04/01/2019
|
EDS
|
|
12
|
CF (Bilaspur)
|
EDS
|
DFO (Bilaspur)
|
04/01/2019
|
EDS
|
|
13
|
DFO (Bilaspur)
|
EDS
|
User Agency (aiimsvinay2010@gmail.com)
|
05/01/2019
|
EDS
|
|
14
|
User Agency (aiimsvinay2010@gmail.com)
|
REPLY
|
DFO (Bilaspur)
|
05/01/2019
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
05/01/2019
|
The corrections have been made by user agency as per observations pointed by moef
|
|
16
|
DFO (Bilaspur)
|
REPLY
|
CF (Bilaspur)
|
05/01/2019
|
The corrections have been made by user agency as per observations pointed by moef
|
|
17
|
CF (Bilaspur)
|
REPLY
|
Nodal Officer
|
06/01/2019
|
The corrections have been made by user agency as per observations pointed by moef
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
07/01/2019
|
Complete reply is submitted.
|
|
19
|
State secretary
|
REPLY
|
Head Office
|
07/01/2019
|
Complete reply is submitted.
|
|