Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Junagadh Circle)
|
EDS
|
DFO (Rajkot)
|
05/10/2021
|
please upload correct site inspection report date
|
|
2
|
DFO (Rajkot)
|
REPLY
|
CF (Junagadh Circle)
|
05/10/2021
|
Uplod correct date
|
|
3
|
Nodal Officer
|
EDS
|
CF (Junagadh Circle)
|
20/10/2021
|
please upload 1.00 CA scheme
|
|
4
|
CF (Junagadh Circle)
|
EDS
|
DFO (Rajkot)
|
20/10/2021
|
as per letter
|
|
5
|
DFO (Rajkot)
|
REPLY
|
CF (Junagadh Circle)
|
22/10/2021
|
CA Scheme Uploded
|
|
6
|
CF (Junagadh Circle)
|
REPLY
|
Nodal Officer
|
22/10/2021
|
c.a scheme uploaded by the division office as per your instuction
|
|