TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/VELEC/16107/2015              (ii). Name of Project for which Forest Land is required : 11 k.v Electric Line Zankhiya              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : As discussed in the for going paragraphs erstwhile method of irrigation is sufficint in present senerio so electricity is the prime requirement for agriculture sector for development              (iv). File no. : 6-GJB01/2018-BHO              (v). State : Gujarat              (vi). Category of the Project : Village Electricity              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.3507
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/VELEC/16107/201527/01/201620/11/2016  02/02/2016   10/02/2017  19/11/2016   22/02/2017   04/07/2017 Gir-West WL :20/07/2017Junagadh WL Circle:
  11/09/2017 (Gir-West WL)

Gujarat:
11/09/2017
Gujarat:
18/11/2017
Gandhinagar:
26/12/2017
14/11/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:24/01/2018  
Replied by State Government(Gujarat) on:27/09/2018  
Query raised by State Government (Gujarat) on:28/02/2018  
Replied by Nodal Officer (Gujarat) on:25/09/2018  
Query raised by Nodal Officer (Gujarat) on:09/04/2018  
Replied by Circle(Junagadh WL Circle) on:03/08/2018  
Query raised by Circle (Junagadh WL Circle) on:23/04/2018  
Replied by DFO (Gir-West WL) on:25/07/2018  
Query raised by DFO (Gir-West WL) on:24/04/2018  
Replied by UA on :24/07/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .