TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/TRANS/41720/2019              (ii). Name of Project for which Forest Land is required : 3 NEW AG CON KHICHA LS 240P1 240P3 397              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For electrification of LS 240P1 (LAND OWNER KISHORBHAI VALJIBHAI DONGA), LS 240P3( LAND OWNER MAHENDRABHAI VALJIBHAI DONGA & 397 (LAND OWNER VASANTBEN GOBARBHAI PRAJAPATI) vill. KHICHA T a. DHARI Dist. AMRELI, 0.0161 ha (230 meter) 11 KV overhead electrical line is proposed for diversion.              (iv). File no. : FCA-1020/3-09/20/SF-160/F              (v). State : Gujarat              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.161
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/GJ/TRANS/41720/201922/08/2019aa23/08/2019   22/09/2019 Gir-East WL :23/09/2019Junagadh WL Circle:
  02/07/2020 (Gir-East WL)

Gujarat:
13/07/2020
Gujarat:
30/07/2020
20/05/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Gujarat) on:02/11/2020  
Replied by Nodal Officer (Gujarat) on:17/03/2021  
Query raised by Nodal Officer (Gujarat) on:17/12/2020  
Replied by Circle(Junagadh WL Circle) on:26/02/2021  
Query raised by Circle (Junagadh WL Circle) on:17/12/2020  
Replied by DFO (Gir-East WL) on:18/02/2021  
NOTE:- Stage-I Approval accorded by : State Government .