TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/TRANS/156865/2022              (ii). Name of Project for which Forest Land is required : Diversion of 0.004 ha. Reserve Forest Land for 11 KV HT Power Supply Cable from Talwada Overhead Water Tank to Terminal Technology Company at Village – Zaroli, Taluka – Umbergaon, District – Valsad.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.004 ha. Reserve Forest Land for 11 KV HT Power Supply Cable from Talwada Overhead Water Tank to Terminal Technology Company at Village – Zaroli, Taluka – Umbergaon, District – Valsad.              (iv). File no. : FC-6/GJB-65/2022-JPR              (v). State : Gujarat              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.004
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/TRANS/156865/202215/06/2022aa16/06/2022   17/06/2022 Valsad-South :17/06/2022Valsad Circle:
  29/06/2022 (Valsad-South)

Gujarat:
26/07/2022
Gujarat:
12/09/2022
Gandhinagar:
01/11/2022
21/12/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Gujarat) on:18/08/2022  
Replied by Circle(Valsad Circle) on:07/09/2022  
Query raised by Circle (Valsad Circle) on:04/07/2022  
Replied by DFO (Valsad-South) on:07/07/2022  
Query raised by Circle (Valsad Circle) on:16/07/2022  
Replied by DFO (Valsad-South) on:19/07/2022  
Query raised by Circle (Valsad Circle) on:26/08/2022  
Replied by DFO (Valsad-South) on:07/09/2022  
Query raised by DFO (Valsad-South) on:06/07/2022  
Replied by UA on :06/07/2022  
Query raised by DFO (Valsad-South) on:06/07/2022  
Replied by UA on :06/07/2022  
Query raised by DFO (Valsad-South) on:18/07/2022  
Replied by UA on :19/07/2022  