TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/TRANS/144417/2021              (ii). Name of Project for which Forest Land is required : 220 KV S/C Transmission Line from Jakhotra to GETCO's 400/220 KV Charanka substation in Santalpur taluka of Patan District in Gujarat State in favor of Torrent Solar Power Private Limited              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 220 KV S/C Transmission line from Jakhotra to GETCO's 400/220 KV Charanka substation in Santalpur taluka of Patan Forest Division & District in Gujarat State in favor of Torrent Solar Power Private Limited, Ahmedabad, Gujarat              (iv). File no. : 6-GJB097/2021-BHO              (v). State : Gujarat              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.5595
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/GJ/TRANS/144417/202107/07/2021aa09/07/2021   15/07/2021 Patan :15/07/2021Kutch Circle:
  31/08/2021 (Patan)

Gujarat:
03/09/2021
Gujarat:
06/09/2021
Gandhinagar:
26/11/2021
11/01/2022
By :Regional Office
Gujarat
28/02/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:06/01/2022  
Replied by State Government(Gujarat) on:10/01/2022  
Query raised by State Government (Gujarat) on:07/01/2022  
Replied by Nodal Officer (Gujarat) on:07/01/2022  
Query raised by Nodal Officer (Gujarat) on:07/01/2022  
Replied by Circle(Kutch Circle) on:07/01/2022  
Query raised by Circle (Kutch Circle) on:07/01/2022  
Replied by DFO (Patan) on:07/01/2022  
Query raised by DFO (Patan) on:10/08/2021  
Replied by UA on :12/08/2021  
Query raised by DFO (Patan) on:07/01/2022  
Replied by UA on :07/01/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Gandhinagar) on:16/03/2022  
Replied by State Government(Gujarat) on:29/08/2022  
Query raised by Regional Office (Gandhinagar) on:07/09/2022  
Query raised by State Government (Gujarat) on:22/03/2022  
Replied by Nodal Officer (Gujarat) on:29/08/2022  
Query raised by State Government (Gujarat) on:19/09/2022  
Replied by Nodal Officer (Gujarat) on:04/07/2023  
Query raised by State Government (Gujarat) on:05/07/2023  
Query raised by Nodal Officer on:06/07/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .