  (i). Proposal No. : FP/GJ/ROAD/38968/2019              (ii). Name of Project for which Forest Land is required : Reconstruction of Gidaradi Bhaniya Road (ODR) Km 11/00 to 17/20 (Working Section Km 12/40 to 17/0)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal For Diversion of 3.45 Ha. Reserved Forest land For the Project of Reconstruction of Gidaradi Bhaniya Road (ODR) Km 11/00 to 17/20 (Working Section Km 12/40 to 17/0)              (iv). File no. : 6-GJB01/2021-BHO              (v). State : Gujarat              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.45
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/ROAD/38968/201916/02/201919/02/2020  23/01/2020  25/03/2019  01/03/2019  18/02/2019   11/03/2020  18/02/2020  16/01/2020  16/03/2019  21/02/2019   16/03/2020   30/03/2020 Gir-East WL :22/04/2020Junagadh WL Circle:
  02/07/2020 (Gir-East WL)

Gujarat:
14/07/2020
Gujarat:
30/07/2020
Gandhinagar:
24/12/2020
30/10/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:29/01/2021  
Replied by State Government(Gujarat) on:07/10/2022  
Query raised by State Government (Gujarat) on:02/11/2020  
Replied by Nodal Officer (Gujarat) on:17/11/2020  
Query raised by State Government (Gujarat) on:15/02/2021  
Replied by Nodal Officer (Gujarat) on:08/09/2022  
Query raised by Nodal Officer (Gujarat) on:24/02/2021  
Replied by Circle(Junagadh WL Circle) on:06/09/2022  
Query raised by Circle (Junagadh WL Circle) on:04/03/2021  
Replied by DFO (Gir-East WL) on:24/08/2022  
Query raised by Circle (Junagadh WL Circle) on:06/09/2022  
Replied by DFO (Gir-East WL) on:06/09/2022  
Query raised by Circle (Junagadh WL Circle) on:06/09/2022  
Replied by DFO (Gir-East WL) on:06/09/2022  
Query raised by DFO (Gir-East WL) on:05/03/2021  
Replied by UA on :23/08/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .