TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/ROAD/155097/2022              (ii). Name of Project for which Forest Land is required : Diversion of 39.14 Ha Forest Land for the Project of “Widening/ Up-gradation of Waghai- Shamghan Section (From Km 59+600 To Km 103+300) of Chikhli- Saputara Road (SH-15) to 4-Laning with Paved Shoulders in Taluka-Waghai & Ahwa, District-Dang, State-Gujarat.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 39.14 Ha Forest Land for the Project of “Widening/ Up-gradation of Waghai- Shamghan Section (From Km 59+600 To Km 103+300) of Chikhli- Saputara Road (SH-15) to 4-Laning with Paved Shoulders in Taluka-Waghai & Ahwa, District-Dang, State-Gujarat.              (iv). State : Gujarat              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 39.14
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/ROAD/155097/202204/05/202221/09/2022  27/06/2022  24/06/2022  10/05/2022  05/05/2022   12/11/2022  20/09/2022  27/06/2022  10/05/2022  07/05/2022   13/05/2022   24/06/2022 Dang-South :29/11/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Dang-South) on:12/12/2022  
Replied by UA on :16/06/2023  
Query raised by DFO (Dang-South) on:06/07/2023  
Replied by UA on :26/10/2023  
Query raised by DFO (Dang-South) on:07/02/2024  
Replied by UA on :23/04/2024  
Query raised by DFO (Dang-South) on:14/05/2024  
Replied by UA on :30/05/2024  
Query raised by DFO (Dang-South) on:11/09/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .