TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/ROAD/152124/2022              (ii). Name of Project for which Forest Land is required : Widening and strengthening of Valsad-Gundlav-Khergam road km 2/0 to 16/0 Ta. Valsad Di. Valsad              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The name of the project is Widening and strengthening of Valsad-Gundlav-Khergam road km 2/0 to 16/0 Ta. Valsad Di. Valsad. This proposal is for widening and strengthening of the existing road from 7 m to 17.25 m and 7m to 12.75 m. It is proposed to construct the road to improve traffic condition.              (iv). State : Gujarat              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 9.85
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/ROAD/152124/202227/06/202228/06/2022   13/07/2022   13/07/2022   25/07/2022 Valsad SF :26/07/2022Bharuch SF Circle:
  09/05/2023 (Valsad SF)

Gujarat:
16/05/2023
Gujarat:
17/05/2023
Gandhinagar:
20/06/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:14/07/2023  
Replied by State Government(Gujarat) on:21/11/2023  
Query raised by State Government (Gujarat) on:24/07/2023  
Replied by Nodal Officer (Gujarat) on:06/11/2023  
Query raised by Nodal Officer (Gujarat) on:25/07/2023  
Replied by Circle(Bharuch SF Circle) on:07/10/2023  
Query raised by Circle (Bharuch SF Circle) on:10/05/2023  
Replied by DFO (Valsad SF) on:10/05/2023  
Query raised by Circle (Bharuch SF Circle) on:10/05/2023  
Replied by DFO (Valsad SF) on:10/05/2023  
Query raised by Circle (Bharuch SF Circle) on:26/07/2023  
Replied by DFO (Valsad SF) on:29/09/2023  
Query raised by Circle (Bharuch SF Circle) on:30/09/2023  
Replied by DFO (Valsad SF) on:06/10/2023  
Query raised by DFO (Valsad SF) on:14/09/2022  
Replied by UA on :01/04/2023  
Query raised by DFO (Valsad SF) on:11/04/2023  
Replied by UA on :03/05/2023  
Query raised by DFO (Valsad SF) on:05/05/2023  
Replied by UA on :08/05/2023  
NOTE:- Proposal is pending at Regional Office .