TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/ROAD/150685/2021              (ii). Name of Project for which Forest Land is required : Construction of proposed R.O.B and its approaches in replacement of existing level crossing No. 21 X  @ Ch: 107.500 on Borsad - Bhadhran Highway near Borsad village of Anand District.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of forest land (Area - 3.4063 Ha) for the nonforest purpose to Construct proposed R.O.B and its approaches in replacement of existing level crossing No. 21 X  @ Ch: 107.500 on Borsad - Bhadhran Highway near Borsad village of Anand District.              (iv). State : Gujarat              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 3.4063
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/ROAD/150685/202130/12/202117/12/2022  31/12/2021   20/12/2022  22/06/2022   23/06/2022   14/12/2022 Anand SF :01/03/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Anand SF) on:06/11/2023  
Replied by UA on :23/04/2024  
Query raised by DFO (Anand SF) on:25/09/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .