  (i). Proposal No. : FP/GJ/ROAD/124586/2021              (ii). Name of Project for which Forest Land is required : Construction of Nada – Kharniya village road in Poshina Taluka of district Sabarkantha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of forest land (Area- 0.999 Ha.) for non forest purpose to construct road Nada - Kharniya village in Poshina taluka of Sabarkantha district.              (iv). State : Gujarat              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.999
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/ROAD/124586/202127/02/2021aa01/03/2021   19/03/2021 Sabarkantha :20/03/2021Gandhinagar Circle:
  11/11/2024 (Sabarkantha)

Gujarat:
26/11/2024
Gujarat:
18/01/2025
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sabarkantha) on:26/03/2021  
Replied by UA on :11/06/2021  
Query raised by DFO (Sabarkantha) on:22/06/2021  
Replied by UA on :03/02/2024  
NOTE:- Proposal is pending at State Government .