Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ahmedabad SF)
|
EDS
|
User Agency (dc@dholerasir.com)
|
16/02/2021
|
Pl. Upload F.R.A.Certi.
|
|
2
|
User Agency (dc@dholerasir.com)
|
REPLY
|
DFO (Ahmedabad SF)
|
21/11/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Ahmedabad SF)
|
EDS
|
User Agency (dc@dholerasir.com)
|
07/12/2022
|
??? ????????? ????? ??? ????? ??????? ????? ????????? ??????? ????
|
|
4
|
User Agency (dc@dholerasir.com)
|
REPLY
|
DFO (Ahmedabad SF)
|
17/05/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Ahmedabad SF)
|
EDS
|
User Agency (dc@dholerasir.com)
|
18/05/2023
|
Letter enclosed herewith
|
|
6
|
User Agency (dc@dholerasir.com)
|
REPLY
|
DFO (Ahmedabad SF)
|
06/07/2023
|
The correction have been made as per the instruction received
|
|
7
|
CF (Ahmedabad SF Circle)
|
EDS
|
DFO (Ahmedabad SF)
|
17/08/2023
|
As per Query Later
|
|
8
|
DFO (Ahmedabad SF)
|
EDS
|
User Agency (dc@dholerasir.com)
|
21/08/2023
|
Report with date on map and proposal
|
|
9
|
User Agency (dc@dholerasir.com)
|
REPLY
|
DFO (Ahmedabad SF)
|
01/09/2023
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Ahmedabad SF)
|
REPLY
|
CF (Ahmedabad SF Circle)
|
06/09/2023
|
Sir, the query given by you has been done
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
12/12/2023
|
The matter was discussed in the REC on dated 11.12.2023 and as per observations of REC State Government is requested to submit following information-
1. Alternative alignments, comparative statement and justification for locating the project in forest land shall be submitted duly certified by the concerned DCF and User Agency.
2. There is a river in the proposed CA land as per DSS analysis. Thus, the State Govt. is requested to submit the revised CA area along with all the details i.e.CA maps, KML file, CA scheme and suitability certificate.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
12/12/2023
|
EDS
|
|
13
|
Nodal Officer
|
EDS
|
CF (Ahmedabad SF Circle)
|
12/12/2023
|
The matter was discussed in the REC on dated 11.12.2023 and as per observations of REC State Government is requested to submit following information- 1. Alternative alignments, comparative statement and justification for locating the project in forest land shall be submitted duly certified by the concerned DCF and User Agency. 2. There is a river in the proposed CA land as per DSS analysis. Thus, the State Govt. is requested to submit the revised CA area along with all the details i.e.CA maps, KML file, CA scheme and suitability certificate.
|
|
14
|
CF (Ahmedabad SF Circle)
|
EDS
|
DFO (Ahmedabad SF)
|
13/12/2023
|
as per nodel latter
|
|
15
|
DFO (Ahmedabad SF)
|
EDS
|
User Agency (dc1-dholerasir@gujarat.gov.in)
|
13/12/2023
|
The matter was discussed in the REC on dated 11.12.2023 and as per observations of REC State Government is requested to submit following information- 1. Alternative alignments, comparative statement and justification for locating the project in forest land shall be submitted duly certified by the concerned DCF and User Agency. 2. There is a river in the proposed CA land as per DSS analysis. Thus, the State Govt. is requested to submit the revised CA area along with all the details i.e.CA maps, KML file, CA scheme and suitability certificate.
|
|
16
|
User Agency (dc1-dholerasir@gujarat.gov.in)
|
REPLY
|
DFO (Ahmedabad SF)
|
01/05/2024
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Ahmedabad SF)
|
REPLY
|
CF (Ahmedabad SF Circle)
|
06/05/2024
|
The correction have been made as per the instruction receive
|
|
18
|
CF (Ahmedabad SF Circle)
|
REPLY
|
Nodal Officer
|
15/05/2024
|
EDS Query solved by DCF Ahmedabad
|
|
19
|
Nodal Officer
|
EDS
|
CF (Ahmedabad SF Circle)
|
15/07/2024
|
As per this office letter Dt-11-06-2024
|
|
20
|
CF (Ahmedabad SF Circle)
|
EDS
|
DFO (Ahmedabad SF)
|
16/07/2024
|
as per nodal officer Remarks
|
|
21
|
DFO (Ahmedabad SF)
|
EDS
|
User Agency (dc1-dholerasir@gujarat.gov.in)
|
19/07/2024
|
as per nodal officer Remarks
|
|
22
|
User Agency (dc1-dholerasir@gujarat.gov.in)
|
REPLY
|
DFO (Ahmedabad SF)
|
29/07/2024
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Ahmedabad SF)
|
REPLY
|
CF (Ahmedabad SF Circle)
|
01/08/2024
|
Sir.
This has been fulfilled in the above proposal
|
|
24
|
CF (Ahmedabad SF Circle)
|
REPLY
|
Nodal Officer
|
16/08/2024
|
As per DCF Complience report
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
30/08/2024
|
AS per the letter
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
09/09/2024
|
Alternative alignments, comparative statement and justification for locating the project in forest land shall be submitted duly certified by the concerned DCF and User Agency is not found in compliance report
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
17/09/2024
|
Alternative Alignments, justification for locating the project is attached herewith.
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
11/10/2024
|
EDS Reply
|
|